Todmorden Moor is an operational 12.3 MW onshore wind farm in Calderdale, generating since 10 September 2014. Planning permission was granted on 1 April 2011, 7 months after submission. Operator of record: Todmorden Moor Wind Farm Ltd.

12.3 MW
Capacity
as recorded in REPD
Operational
Status
since 10 September 2014
Wind Onshore
Technology
Todmorden Moor Wind Farm Ltd
Calderdale
Authority
England

Planning and build timeline

Application submitted10 September 2010
Permission granted1 April 2011
7 months after submission
Operational10 September 2014
41 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Calderdale: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Todmorden Moor’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 5 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
10.20.5 km
Wind Onshore · Operational
23.84.4 km
Wind Onshore · Operational
13.64.8 km
Wind Onshore · Operational
9.65.5 km
Wind Onshore · Operational
165.5 km
Landfill Gas · Operational
26.9 km
Wind Onshore · Operational
658 km
Landfill Gas · Operational
1.69.1 km

How big is Todmorden Moor?

Todmorden Moor has a recorded installed capacity of 12.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Todmorden Moor?

REPD records the operator as Todmorden Moor Wind Farm Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Todmorden Moor approved and built?

The application was submitted on 10 September 2010. Permission was granted on 1 April 2011, 7 months later. The site became operational on 10 September 2014, 41 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4419.