Novarly ParcelRenewable sites

Renewable sitesTodmorden Moor

Todmorden Moor

Todmorden Moor is operational in Calderdale with a recorded capacity of 12.3 MW, and has been generating since 2014-09-10.

12.3 MW
Capacity
as recorded in REPD
Operational
Status
since 2014-09-10
Wind Onshore
Technology
Todmorden Moor Wind Farm Ltd
Calderdale
Authority
England

Planning and build timeline

Application submitted2010-09-10
Permission granted2011-04-01
7 months after submission
Operational2014-09-10
41 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Grade 5 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Reaps Moss Wind Farm
Wind Onshore · Operational
10.20.5 km
Crook Hill (Rochdale MBC) 2 of 2
Wind Onshore · Operational
23.84.4 km
Crook Hill (Calderdale MBC) 1 of 2
Wind Onshore · Operational
13.64.8 km
Coal Clough Wind Farm
Wind Onshore · Operational
9.65.5 km
Coal Clough Wind Farm Repowering
Wind Onshore · Operational
165.5 km
Deerplay Landfill Site
Landfill Gas · Operational
26.9 km
Scout Moor Windfarm
Wind Onshore · Operational
658 km
Horncliffe Quarry (Extension)
Landfill Gas · Operational
19.1 km

How big is Todmorden Moor?

Todmorden Moor has a recorded installed capacity of 12.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Todmorden Moor?

REPD records the operator as Todmorden Moor Wind Farm Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Todmorden Moor approved and built?

The application was submitted on 2010-09-10. Permission was granted on 2011-04-01, 7 months later. The site became operational on 2014-09-10, 41 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4419.