Renewable sites › Crook Hill (Calderdale MBC) 1 of 2
Crook Hill (Calderdale MBC) 1 of 2
Crook Hill (Calderdale MBC) 1 of 2 is operational in Rochdale with a recorded capacity of 13.6 MW, and has been generating since 2015-12-01.
Planning and build timeline
| Application submitted | 2008-08-04 |
| Permission granted | 2009-10-12 14 months after submission |
| Operational | 2015-12-01 74 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 5 agricultural land.
- Green Belt — Rochdale
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Crook Hill (Rochdale MBC) 2 of 2 Wind Onshore · Operational | 23.8 | 0.3 km |
Todmorden Moor Wind Onshore · Operational | 12.3 | 4.8 km |
Reaps Moss Wind Farm Wind Onshore · Operational | 10.2 | 5.1 km |
Gipsy Lane Battery · Under Construction | 20 | 9 km |
Astra Centre, Royal Barn Road - Energy Storage Battery · Under Construction | 40 | 9.1 km |
Coal Clough Wind Farm Wind Onshore · Operational | 9.6 | 9.4 km |
Coal Clough Wind Farm Repowering Wind Onshore · Operational | 16 | 9.4 km |
Scout Moor Windfarm Wind Onshore · Operational | 65 | 10.3 km |
How big is Crook Hill (Calderdale MBC) 1 of 2?
Crook Hill (Calderdale MBC) 1 of 2 has a recorded installed capacity of 13.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Crook Hill (Calderdale MBC) 1 of 2?
REPD records the operator as Infrared Capital Partners. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Crook Hill (Calderdale MBC) 1 of 2 approved and built?
The application was submitted on 2008-08-04. Permission was granted on 2009-10-12, 14 months later. The site became operational on 2015-12-01, 74 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4354.