Renewable sites › Scout Moor Windfarm
Scout Moor Windfarm
Scout Moor Windfarm is operational in Rossendale with a recorded capacity of 65 MW, and has been generating since 2008-06-01.
Planning and build timeline
| Application submitted | 2003-06-30 |
| Permission granted | 2005-05-25 23 months after submission |
| Operational | 2008-06-01 36 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 5 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Rossendale’s record on onshore wind
Rossendale has decided 5 onshore wind schemes and approved 40%, taking a median of 15.8 months. See every onshore wind scheme decision in Rossendale →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Rossendale Power Landfill Gas · Operational | 1.6 | 2.5 km |
Horncliffe Quarry Landfill Gas · Operational | 1 | 2.5 km |
Horncliffe Quarry (Extension) Landfill Gas · Operational | 1 | 2.5 km |
Reaps Moss Wind Farm Wind Onshore · Operational | 10.2 | 7.5 km |
Todmorden Moor Wind Onshore · Operational | 12.3 | 8 km |
Lascar Works Battery · Operational | 20 | 8.2 km |
Hyndburn Wind Farm Wind Onshore · Operational | 24 | 9.5 km |
Chamber House Solar Photovoltaics · Under Construction | 3.99 | 9.5 km |
How big is Scout Moor Windfarm?
Scout Moor Windfarm has a recorded installed capacity of 65 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Scout Moor Windfarm?
REPD records the operator as Munich Re (previously Peel). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Scout Moor Windfarm approved and built?
The application was submitted on 2003-06-30. Permission was granted on 2005-05-25, 23 months later. The site became operational on 2008-06-01, 36 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3177.