Renewable sites › Tilbury Docks
Tilbury Docks
Tilbury Docks is an operational 12 MW onshore wind farm in Thurrock, generating since 25 March 2013. Planning permission was granted on 13 May 2008, 5 months after submission. Operator of record: Scottish Equity Partners.
Planning and build timeline
| Application submitted | 20 December 2007 |
| Permission granted | 13 May 2008 5 months after submission |
| Operational | 25 March 2013 58 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Thurrock: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Tilbury Docks’s recorded coordinate — swap in your own postcode or coordinates.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Biomass (dedicated) · Operational | 43 | 1 km |
Battery · Operational | 3.8 | 1.6 km |
Solar Photovoltaics · Operational | 4 | 1.6 km |
Battery · Operational | 150 | 3.3 km |
Battery · Operational | 11 | 4.9 km |
Battery · Operational | 7.5 | 6.1 km |
Solar Photovoltaics · Operational | 5 | 6.2 km |
Landfill Gas · Operational | 4.5 | 6.6 km |
How big is Tilbury Docks?
Tilbury Docks has a recorded installed capacity of 12 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Tilbury Docks?
REPD records the operator as Scottish Equity Partners. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Tilbury Docks approved and built?
The application was submitted on 20 December 2007. Permission was granted on 13 May 2008, 5 months later. The site became operational on 25 March 2013, 58 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3982.