Renewable sites › Littlebrook Battery Storage
Littlebrook Battery Storage
Littlebrook Battery Storage is operational in Dartford with a recorded capacity of 7.5 MW, and has been generating since 2017-12-01.
Planning and build timeline
| Application submitted | 2016-07-14 |
| Permission granted | 2016-09-12 2 months after submission |
| Operational | 2017-12-01 15 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Dartford’s record on battery storage
Dartford has decided 5 battery storage schemes and approved 80%, taking a median of 5.2 months. See every battery storage scheme decision in Dartford →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Longreach STW - extension Sewage Sludge Digestion · Operational | 1.1 | 1.4 km |
Sandy Lane Landfill Scheme Landfill Gas · Operational | 2.3 | 5 km |
Aveley Landfill Scheme Landfill Gas · Operational | 2.1 | 5.1 km |
Aveley Landfill Gas · Operational | 1.2 | 5.1 km |
Rainham Landfill Scheme, Phase I Landfill Gas · Operational | 3.9 | 5.2 km |
Rainham Phase II Landfill Gas · Operational | 17 | 5.2 km |
St Margaret's Farm - Green Waste Composting Facility Biomass (dedicated) · Under Construction | — | 5.5 km |
Tilbury Docks Wind Onshore · Operational | 12 | 6.1 km |
How big is Littlebrook Battery Storage?
Littlebrook Battery Storage has a recorded installed capacity of 7.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Littlebrook Battery Storage?
REPD records the operator as Camborne Energy / Noriker Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Littlebrook Battery Storage approved and built?
The application was submitted on 2016-07-14. Permission was granted on 2016-09-12, 2 months later. The site became operational on 2017-12-01, 15 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 20327.