Tilbury Green Power

Tilbury Green Power is operational in Thurrock with a recorded capacity of 43 MW, and has been generating since 2017-10-26.

43 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-10-26
Biomass (dedicated)
Technology
Tilbury Green Power
Thurrock
Authority
England

Planning and build timeline

Application submitted2008-02-07
Permission granted2009-08-27
19 months after submission
Operational2017-10-26
98 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
London Distribution Park
Battery · Operational
3.80.8 km
Tilbury LCY2
Solar Photovoltaics · Operational
40.8 km
Tilbury Docks
Wind Onshore · Operational
121 km
Thurrock Flexible Generation Plant
Battery · Operational
1502.4 km
Barvills Solar Farm
Solar Photovoltaics · Operational
55.3 km
Broadditch Battery Energy
Battery · Operational
115.4 km
Mucking Gas 2 Landfill Scheme
Landfill Gas · Operational
3.86.4 km
Mucking Gas 3 Landfill Scheme
Landfill Gas · Operational
3.96.4 km

How big is Tilbury Green Power?

Tilbury Green Power has a recorded installed capacity of 43 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Tilbury Green Power?

REPD records the operator as Tilbury Green Power. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Tilbury Green Power approved and built?

The application was submitted on 2008-02-07. Permission was granted on 2009-08-27, 19 months later. The site became operational on 2017-10-26, 98 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 152.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council