Renewable sites › Ockendon 'B' Landfill Scheme
Ockendon 'B' Landfill Scheme
Ockendon 'B' Landfill Scheme is operational in Thurrock with a recorded capacity of 4.5 MW, and has been generating since 1998-12-09.
Planning and build timeline
| Application submitted | 1997-05-15 |
| Permission granted | 1997-06-26 1 months after submission |
| Operational | 1998-12-09 17 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 1 agricultural land.
- Green Belt — Thurrock
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Ockendon Area III Landfill Gas · Operational | 8.5 | 1.3 km |
Medebridge Road - Solar Farm Solar Photovoltaics · Operational | 49.9 | 1.4 km |
Ockendon Landfill Solar Farm Solar Photovoltaics · Operational | 38 | 1.4 km |
Little Belhus Restoration Site Wind Onshore · Operational | 1 | 2.5 km |
Fen Lane, Bulphan Solar Farm Solar Photovoltaics · Under Construction | 49.9 | 3.1 km |
Bulphan Fen Solar Farm & Battery Storage Solar Photovoltaics · Under Construction | 49.9 | 3.4 km |
Bulphan Fen Solar Farm & Battery Storage Battery · Under Construction | — | 3.4 km |
Clay Tye Farm Phase 1 - Storage Facility Battery · Operational | 49.5 | 4.4 km |
How big is Ockendon 'B' Landfill Scheme?
Ockendon 'B' Landfill Scheme has a recorded installed capacity of 4.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Ockendon 'B' Landfill Scheme?
REPD records the operator as Haul Waste Disposal Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Ockendon 'B' Landfill Scheme approved and built?
The application was submitted on 1997-05-15. Permission was granted on 1997-06-26, 1 months later. The site became operational on 1998-12-09, 17 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 523.
Novarly Parcel · official public data, read properly · parcel.novarly.com