Novarly ParcelRenewable sites

Renewable sitesThornog Windfarm

Thornog Windfarm

Thornog Windfarm is an operational 9.2 MW onshore wind farm in Fermanagh and Omagh, generating since 22 September 2014. Planning permission was granted on 1 March 2008, 30 months after submission. Operator of record: Energia Renewables.

9.2 MW
Capacity
as recorded in REPD
Operational
Status
since 22 September 2014
Wind Onshore
Technology
Energia Renewables
Fermanagh and Omagh
Authority
Northern Ireland

Planning and build timeline

Application submitted8 September 2005
Permission granted1 March 2008
30 months after submission
Operational22 September 2014
79 months after consent

Screening a site of your own?

RedlineUK · £39

Fermanagh and Omagh approves 92% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Thornog Windfarm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Fermanagh and Omagh’s record on onshore wind

Fermanagh and Omagh has decided 66 onshore wind schemes and approved 92%, taking a median of 20.9 months. See every onshore wind scheme decision in Fermanagh and Omagh

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
9.20 km
Wind Onshore · Operational
253.3 km
Wind Onshore · Operational
6.93.3 km
Wind Onshore · Operational
10.54.3 km
Wind Onshore · Operational
304.3 km
Wind Onshore · Operational
94.9 km
Wind Onshore · Under Construction
277.4 km
Wind Onshore · Operational
38.48.8 km

How big is Thornog Windfarm?

Thornog Windfarm has a recorded installed capacity of 9.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Thornog Windfarm?

REPD records the operator as Energia Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Thornog Windfarm approved and built?

The application was submitted on 8 September 2005. Permission was granted on 1 March 2008, 30 months later. The site became operational on 22 September 2014, 79 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4053.