Onshore wind planning in Fermanagh and Omagh

Fermanagh and Omagh has decided 66 onshore wind schemes and approved 92% of them, taking a median of 20.9 months to decide. Consented capacity: 552 MW. 12 applications still awaiting a decision.

92%
Approved
61 granted · 5 refused
20.9 mo
Median decision
UK 11.5 mo
552 MW
Consented
93 MW refused
11
Appeals
5 allowed on appeal

How Fermanagh and Omagh compares

Against the 75 UK authorities with 5+ onshore wind decisions, Fermanagh and Omagh sits in the 91st percentile for approval rate (24 points above the England average) and the 18th percentile for speed.

Decisions by year

815Approved — 4 (2010)410Approved — 2 (2011)2Approved — 3 (2012)312Approved — 2 (2013)2Approved — 1 (2014)Refused — 1 (2014)214Approved — 3 (2015)Refused — 1 (2015)4Approved — 1 (2016)116Approved — 1 (2017)Refused — 2 (2017)3Approved — 1 (2018)118Approved — 5 (2019)5Approved — 12 (2020)1220Approved — 8 (2021)8Approved — 1 (2022)122Approved — 1 (2023)1Approved — 2 (2024)224
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (93)

SchemeMWStatusDecided
Wind Turbine Development in Omagh
Private Developer · LA10/2025/0305/F
Application Submitted2025-03-20
Wind Turbine Development in Enniskillen
Private Developer · LA10/2025/0296/F
Application Submitted2025-03-19
Wind Turbine Development in Derrygonnelly
Private Developer · LA10/2025/0208/F
Application Submitted2025-02-26
Wind Turbine Development in Fintona
Unkown · LA10/2025/0177/F
Application Submitted2025-02-17
Wind Turbine Development in Strabane
Private Developer · LA11/2024/0844/F
0.3Application Submitted2024-11-12
Wind Turbine Development in Carrickmore
Private Developer · LA10/2024/0928/F
Application Submitted2024-09-30
Wind Turbine in Irvinestown
Drumhoney Caravan Park · LA10/2023/1510/F · 14.6 mo to decide
0.85Awaiting Construction2024-05-24
Wind Turbine Alterations in Maguiresbridge
Foydragh Wind Limited · LA10/2024/0341/F
Application Submitted2024-04-25
Drumbarley Road, Drumquin - Wind Turbine
Private Developer · LA10/2024/0288/F
Application Submitted2024-04-08
20 Crannoge Road - Wind Turbine
HHT Renewables · LA10/2023/1390/F · 12 mo to decide
Awaiting Construction2024-01-26
Segully Road, Drumquin - Wind Turbine
Segully Energy Limited · LA10/2023/1729/F · 7 mo to decide
2Awaiting Construction2023-12-08
Camlough Road
Arena Capital Partners Limited · LA10/2021/0016/F · 16.1 mo to decide
0.25Awaiting Construction2022-04-25
Replacement Wind Turbine
McKernaghan Architectural Service Limited · LA10/2021/0093/F · 10.3 mo to decide
0.4Awaiting Construction2021-12-01
The Kids Road, Garraroosky
CD Consulting · LA10/2021/1040/F · 2.2 mo to decide
0.25Awaiting Construction2021-10-25
The Kids Road, Garraroosky
CD Consulting · LA10/2020/0456/F · 16.6 mo to decide
0.25Awaiting Construction2021-10-25
Creggan Road Wind Turbine
John McKernan · LA10/2021/0286/F · 6.5 mo to decide
0.25Awaiting Construction2021-09-23
Glen Road
Private Developer · LA10/2020/1014/F · 7 mo to decide
0.25Awaiting Construction2021-05-17
Killymendon (Replacement Turbine)
Private Developer · LA10/2019/0978/F · 18.9 mo to decide
0.3Awaiting Construction2021-03-11
Edenmore Road
Private Developer · LA10/2020/0160/F · 12.2 mo to decide
0.3Awaiting Construction2021-02-19
Killymittan Road
Private Developer · LA10/2020/0168/F · 11 mo to decide
0.3Awaiting Construction2021-01-15
Mullanmore Road
Arena Capital Partners Limited · LA10/2021/0017/F
0.25Application Submitted2020-12-22
Mulnahorn Road
Private Developer · LA10/2020/0989/F · 2.2 mo to decide
0.25Awaiting Construction2020-12-17
Lissan Lane
Fermanagh GAA · LA10/2019/1300/F · 11.5 mo to decide
0.3Awaiting Construction2020-10-28
Shankill Road
Private Developer · LA10/2020/0081/F · 9 mo to decide
0.3Awaiting Construction2020-10-23
Coa Road
Private Developer · LA10/2019/1285/F · 11.3 mo to decide
0.3Awaiting Construction2020-10-15
Derryallen Road
Private Developer · LA10/2019/1270/F · 11.4 mo to decide
0.5Awaiting Construction2020-10-12
Barony Road
Private Developer · LA10/2020/0721/F · 2 mo to decide
0.2Awaiting Construction2020-10-08
Callagheen Road
Private Developer · LA10/2019/1354/F · 10.2 mo to decide
0.3Awaiting Construction2020-10-02
Coa Chapel Road
Thompson Renewables · LA10/2019/0564/F · 16.4 mo to decide
0.3Awaiting Construction2020-09-24
Rosnareen Road
Golan Wind · LA10/2019/1475/F · 8.6 mo to decide
0.3Awaiting Construction2020-09-08
Tursallagh Road
Private Developer · LA10/2020/0603/F
0.3Application Submitted2020-07-08
Drumcor Road
Private Developer · LA10/2019/1228/F · 8.7 mo to decide
1Awaiting Construction2020-07-08
Rockstown Road
Private Developer · LA10/2019/1089/F · 9.1 mo to decide
0.3Awaiting Construction2020-06-15
Nutfield Road
Private Developer · LA10/2019/1229/F
0.3Application Withdrawn2020-05-26
Craighill Road
Arena Capital Partners · LA10/2019/1215/F · 4.4 mo to decide
0.3Awaiting Construction2020-02-25
Mullawinny Road (Replacement Turbine)
Private Developer · LA10/2019/0947/F
0.2Application Withdrawn2020-02-06
Aghnaglea Road (relplacement turbine)
Private Developer · LA10/2019/0720/F · 3.6 mo to decide
0.2Awaiting Construction2019-10-03
Breagho Road
Mullinamoot · LA10/2019/1084/F
0.5Application Submitted2019-09-11
Derrylin Rd and Marble Arch Rd Junction
MCM Renewables · LA10/2019/0173/F
0.8Application Withdrawn2019-06-28
Barony Road
Private Developer · LA10/2019/0323/F · 3.4 mo to decide
0.3Awaiting Construction2019-06-24
Ballybrack Road
Private Developer · LA10/2018/1548/F · 4.8 mo to decide
0.2Awaiting Construction2019-05-02
Camlough Road
Private Developer · LA10/2019/0320/F · 1.6 mo to decide
0.3Awaiting Construction2019-04-30
Crockanboy Road (resubmission)
Private Developer · LA10/2018/1476/F
4.2Application Withdrawn2019-04-19
Cloghfin Road
MPG Wind · LA10/2018/0763/F · 9.9 mo to decide
4.8Awaiting Construction2019-04-17
Glengesh Lower Forest (Murley)
Renewable Energy Systems (RES) · LA09/2015/0460/F · 30.8 mo to decide
20.7Awaiting Construction2018-05-08
Curraghamulkin (Dooish Wind Farm)
DW Consultancy · K/2008/0334/F · 116 mo to decide
30Operational2017-11-10
Barony
Island Renewable Energy · LA10/2015/0283/F · 22.8 mo to decide
9.2Appeal Refused2017-05-19
Lisnaharney Road Wind Farm
ARC NI 3 Ltd/Windyfields (Renewable Energy International) · K/2013/0181/F · 45.2 mo to decide
42Appeal Refused2017-01-20
Dunnaree Hill Wind Farm
Scottish and Southern Energy (SSE) · K/2011/0237/F
15Application Withdrawn2016-02-01
Bessy Bell 2 Extension
Scottish and Southern Energy (SSE) · K/2013/0145/F · 33.1 mo to decide
9Planning Permission Expired2016-01-18
Ora More Extension
Renewable Energy Systems (RES) · L/2013/0625/F · 24.8 mo to decide
6Planning Permission Expired2015-12-17
Derrynaveigh Wind Farm
Derrynaveigh Wind Farm Ltd · L/2013/0623/F · 22.1 mo to decide
5.6Application Refused2015-09-24
Garranbane Wind Farm
Garranbane Wind Farm Ltd · L/2013/0622/F · 19.9 mo to decide
8Appeal Withdrawn2015-07-20
Slieveard Wind Farm
Slieveard Wind Farm Ltd · K/2013/0102/F · 27.7 mo to decide
17.5Appeal Withdrawn2015-07-16
Clunahill Wind Farm
ESB (Hibernian Wind) · K/2007/0547/F · 87.9 mo to decide
21Awaiting Construction2015-02-20
Altamuskin Extension
Altamuskin Windfarm (Energia) · K/2011/0239/F · 45.5 mo to decide
7.1Operational2015-01-28
Teiges
Energia · L/2008/0459/F · 80.4 mo to decide
11Operational2014-12-12
Crocknamona Wind Farm
Scottish and Southern Energy (SSE) · K/2010/0758/F · 46.8 mo to decide
17.5Application Refused2014-11-13
490m north East of no 64 Backglen Road
Private Developer · K/2014/0477/F
2Appeal Withdrawn2014-10-23
Ref 4920
Private Developer · K/2014/0440/F
2Appeal Withdrawn2014-09-29
Carricknabrattoge
Wind Developments · L/2002/1183/F
12.1Application Withdrawn2013-10-08
Belmore Mountain
Airtricity Developments (UK) · L/2005/0377/F
30Application Withdrawn2013-10-08
Garrane
B9 Wind Farm Developments · L/2001/1346/F
17.5Application Withdrawn2013-10-08
Slieveglass
Slieveglass wind farm (Energia) · J/2008/0088 · 64.5 mo to decide
6.9Operational2013-06-12
Molly Mountain
Erne Concrete Pumping · L/2008/1113/F · 53.6 mo to decide
15Operational2013-02-01
Pigeon Top
Energia · K/2011/0592/F · 13.7 mo to decide
27Under Construction2012-11-15
Thornog Windfarm Extension
Energia Renewables · K/2009/0243/F · 41.4 mo to decide
9.2Operational2012-09-11
Crockbaravally Wind Farm
Golden Square Energy · K/2008/1153/F · 38 mo to decide
7.5Operational2012-03-05
Castlecraig
Renewable Energy Systems (RES) · K/2006/1934/F · 53.5 mo to decide
25Operational2011-06-01
Ora More
Natural Power · L/2005/3070/F · 63.4 mo to decide
15Operational2011-03-30
Tullinoid
Fermanagh Wind Energy · L/2004/0472/F
6Application Withdrawn2011-01-18
Pigeon Top
TCI Renewables · K/2009/0081 · 23.1 mo to decide
20.7Revised2010-12-13
Crockagarron Ext
Northern Wind Power� · K/2009/0182/F · 21.2 mo to decide
2.5Operational2010-12-08
Inishative
Gaelectric Developments/ CGN Europe Energy · K/2006/1793/F · 48.1 mo to decide
13.8Operational2010-11-12
Crockdun
ESB (Northern Wind Power) · K/2006/0074/F · 55.7 mo to decide
12.5Operational2010-09-13
Cregganconroe
Gaelectric Developments/ CGN Europe Energy · K/2006/0242/F · 47.3 mo to decide
13.8Operational2010-09-08
Callagheen Ext
Scottish Power Renewables · L/2007/1772/F
13.8Application Withdrawn2010-04-01
Pollnalaght (Cornavarrow)
Energia · K/2006/1368/F · 39.8 mo to decide
38.4Operational2009-10-16
Gortgall
Unknown · L/2006/1197 · 40.7 mo to decide
18.4Application Refused2009-07-21
Ballyreagh, Tempo
TCI Renewables · L/2006/2371/F · 28.8 mo to decide
2.5Abandoned2009-05-11
Gortfinbar
Energia Renewables · K/2006/1089/F · 37.1 mo to decide
15Operational2009-05-07
Altamuskin
Altamuskin Windfarm (Energia) · K/2006/0164/F · 33.9 mo to decide
7.1Operational2008-12-02
Screggagh
Screggagh Windfarm · K/2005/0810/F · 36.8 mo to decide
19.5Operational2008-05-13
Tappaghan Extension
Greencoat UK Wind · L/2006/1553/F · 34.6 mo to decide
9Operational2008-05-01
Thornog Windfarm
Energia Renewables · K/2005/1786/F · 29.7 mo to decide
9.2Operational2008-03-01
Crockagarran
ESB · K/2005/0537/F · 23.6 mo to decide
15Operational2007-06-25
Slieve Divena Phase 2 Wind Farm
Scottish and Southern Energy (SSE) · K/2005/1691/F · 20.7 mo to decide
18.8Operational2007-06-06
Slieve Divena Phase 1 Wind Farm
Greencoat (formerly Infinis/SSE) · K/2005/0597/F · 26.5 mo to decide
30Operational2007-05-17
Slieve Rushen Extension
Unknown · L/2004/2058/F · 22.9 mo to decide
54Operational2006-10-01
Land approx 75m South of 141
Private Developer · K/2005/0183/F · 2.7 mo to decide
20Operational2005-04-26
Callagheen
B9 / Renewable Energy Systems (RES) · L2001/1514 · 27.4 mo to decide
22.8Operational2004-04-08
Tappaghan
Greencoat UK Wind · L/2002/1042/F · 15.1 mo to decide
19.5Operational2003-11-03
Slieve Rushen Phase 1 Wind Farm
Sean Quinn Group · 5.6 mo to decide
5Operational1992-11-02

Does Fermanagh and Omagh approve onshore wind schemes?

Yes — of the 66 onshore wind schemes Fermanagh and Omagh has decided, 92% were approved (61 granted, 5 refused). The UK-wide rate for onshore wind is 68%.

How long does a onshore wind scheme application take in Fermanagh and Omagh?

The median time from application to decision is 20.9 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has Fermanagh and Omagh consented?

552 MW has been consented across 61 approved schemes, with 93 MW refused. A further 12 applications awaits a decision.

Other technologies in Fermanagh and Omagh

Solar in Fermanagh and OmaghBattery storage in Fermanagh and Omagh

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.