Renewable planning › Onshore wind › Fermanagh and Omagh
Onshore wind planning in Fermanagh and Omagh
Fermanagh and Omagh has decided 66 onshore wind schemes and approved 92% of them, taking a median of 20.9 months to decide. Consented capacity: 552 MW. 12 applications still awaiting a decision.
How Fermanagh and Omagh compares
Against the 75 UK authorities with 5+ onshore wind decisions, Fermanagh and Omagh sits in the 91st percentile for approval rate (24 points above the England average) and the 18th percentile for speed.
Decisions by year
Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.
Every recorded scheme (93)
| Scheme | MW | Status | Decided |
|---|---|---|---|
Wind Turbine Development in Omagh Private Developer · LA10/2025/0305/F | — | Application Submitted | 2025-03-20 |
Wind Turbine Development in Enniskillen Private Developer · LA10/2025/0296/F | — | Application Submitted | 2025-03-19 |
Wind Turbine Development in Derrygonnelly Private Developer · LA10/2025/0208/F | — | Application Submitted | 2025-02-26 |
Wind Turbine Development in Fintona Unkown · LA10/2025/0177/F | — | Application Submitted | 2025-02-17 |
Wind Turbine Development in Strabane Private Developer · LA11/2024/0844/F | 0.3 | Application Submitted | 2024-11-12 |
Wind Turbine Development in Carrickmore Private Developer · LA10/2024/0928/F | — | Application Submitted | 2024-09-30 |
Wind Turbine in Irvinestown Drumhoney Caravan Park · LA10/2023/1510/F · 14.6 mo to decide | 0.85 | Awaiting Construction | 2024-05-24 |
Wind Turbine Alterations in Maguiresbridge Foydragh Wind Limited · LA10/2024/0341/F | — | Application Submitted | 2024-04-25 |
Drumbarley Road, Drumquin - Wind Turbine Private Developer · LA10/2024/0288/F | — | Application Submitted | 2024-04-08 |
20 Crannoge Road - Wind Turbine HHT Renewables · LA10/2023/1390/F · 12 mo to decide | — | Awaiting Construction | 2024-01-26 |
Segully Road, Drumquin - Wind Turbine Segully Energy Limited · LA10/2023/1729/F · 7 mo to decide | 2 | Awaiting Construction | 2023-12-08 |
Camlough Road Arena Capital Partners Limited · LA10/2021/0016/F · 16.1 mo to decide | 0.25 | Awaiting Construction | 2022-04-25 |
Replacement Wind Turbine McKernaghan Architectural Service Limited · LA10/2021/0093/F · 10.3 mo to decide | 0.4 | Awaiting Construction | 2021-12-01 |
The Kids Road, Garraroosky CD Consulting · LA10/2021/1040/F · 2.2 mo to decide | 0.25 | Awaiting Construction | 2021-10-25 |
The Kids Road, Garraroosky CD Consulting · LA10/2020/0456/F · 16.6 mo to decide | 0.25 | Awaiting Construction | 2021-10-25 |
Creggan Road Wind Turbine John McKernan · LA10/2021/0286/F · 6.5 mo to decide | 0.25 | Awaiting Construction | 2021-09-23 |
Glen Road Private Developer · LA10/2020/1014/F · 7 mo to decide | 0.25 | Awaiting Construction | 2021-05-17 |
Killymendon (Replacement Turbine) Private Developer · LA10/2019/0978/F · 18.9 mo to decide | 0.3 | Awaiting Construction | 2021-03-11 |
Edenmore Road Private Developer · LA10/2020/0160/F · 12.2 mo to decide | 0.3 | Awaiting Construction | 2021-02-19 |
Killymittan Road Private Developer · LA10/2020/0168/F · 11 mo to decide | 0.3 | Awaiting Construction | 2021-01-15 |
Mullanmore Road Arena Capital Partners Limited · LA10/2021/0017/F | 0.25 | Application Submitted | 2020-12-22 |
Mulnahorn Road Private Developer · LA10/2020/0989/F · 2.2 mo to decide | 0.25 | Awaiting Construction | 2020-12-17 |
Lissan Lane Fermanagh GAA · LA10/2019/1300/F · 11.5 mo to decide | 0.3 | Awaiting Construction | 2020-10-28 |
Shankill Road Private Developer · LA10/2020/0081/F · 9 mo to decide | 0.3 | Awaiting Construction | 2020-10-23 |
Coa Road Private Developer · LA10/2019/1285/F · 11.3 mo to decide | 0.3 | Awaiting Construction | 2020-10-15 |
Derryallen Road Private Developer · LA10/2019/1270/F · 11.4 mo to decide | 0.5 | Awaiting Construction | 2020-10-12 |
Barony Road Private Developer · LA10/2020/0721/F · 2 mo to decide | 0.2 | Awaiting Construction | 2020-10-08 |
Callagheen Road Private Developer · LA10/2019/1354/F · 10.2 mo to decide | 0.3 | Awaiting Construction | 2020-10-02 |
Coa Chapel Road Thompson Renewables · LA10/2019/0564/F · 16.4 mo to decide | 0.3 | Awaiting Construction | 2020-09-24 |
Rosnareen Road Golan Wind · LA10/2019/1475/F · 8.6 mo to decide | 0.3 | Awaiting Construction | 2020-09-08 |
Tursallagh Road Private Developer · LA10/2020/0603/F | 0.3 | Application Submitted | 2020-07-08 |
Drumcor Road Private Developer · LA10/2019/1228/F · 8.7 mo to decide | 1 | Awaiting Construction | 2020-07-08 |
Rockstown Road Private Developer · LA10/2019/1089/F · 9.1 mo to decide | 0.3 | Awaiting Construction | 2020-06-15 |
Nutfield Road Private Developer · LA10/2019/1229/F | 0.3 | Application Withdrawn | 2020-05-26 |
Craighill Road Arena Capital Partners · LA10/2019/1215/F · 4.4 mo to decide | 0.3 | Awaiting Construction | 2020-02-25 |
Mullawinny Road (Replacement Turbine) Private Developer · LA10/2019/0947/F | 0.2 | Application Withdrawn | 2020-02-06 |
Aghnaglea Road (relplacement turbine) Private Developer · LA10/2019/0720/F · 3.6 mo to decide | 0.2 | Awaiting Construction | 2019-10-03 |
Breagho Road Mullinamoot · LA10/2019/1084/F | 0.5 | Application Submitted | 2019-09-11 |
Derrylin Rd and Marble Arch Rd Junction MCM Renewables · LA10/2019/0173/F | 0.8 | Application Withdrawn | 2019-06-28 |
Barony Road Private Developer · LA10/2019/0323/F · 3.4 mo to decide | 0.3 | Awaiting Construction | 2019-06-24 |
Ballybrack Road Private Developer · LA10/2018/1548/F · 4.8 mo to decide | 0.2 | Awaiting Construction | 2019-05-02 |
Camlough Road Private Developer · LA10/2019/0320/F · 1.6 mo to decide | 0.3 | Awaiting Construction | 2019-04-30 |
Crockanboy Road (resubmission) Private Developer · LA10/2018/1476/F | 4.2 | Application Withdrawn | 2019-04-19 |
Cloghfin Road MPG Wind · LA10/2018/0763/F · 9.9 mo to decide | 4.8 | Awaiting Construction | 2019-04-17 |
Glengesh Lower Forest (Murley) Renewable Energy Systems (RES) · LA09/2015/0460/F · 30.8 mo to decide | 20.7 | Awaiting Construction | 2018-05-08 |
Curraghamulkin (Dooish Wind Farm) DW Consultancy · K/2008/0334/F · 116 mo to decide | 30 | Operational | 2017-11-10 |
Barony Island Renewable Energy · LA10/2015/0283/F · 22.8 mo to decide | 9.2 | Appeal Refused | 2017-05-19 |
Lisnaharney Road Wind Farm ARC NI 3 Ltd/Windyfields (Renewable Energy International) · K/2013/0181/F · 45.2 mo to decide | 42 | Appeal Refused | 2017-01-20 |
Dunnaree Hill Wind Farm Scottish and Southern Energy (SSE) · K/2011/0237/F | 15 | Application Withdrawn | 2016-02-01 |
Bessy Bell 2 Extension Scottish and Southern Energy (SSE) · K/2013/0145/F · 33.1 mo to decide | 9 | Planning Permission Expired | 2016-01-18 |
Ora More Extension Renewable Energy Systems (RES) · L/2013/0625/F · 24.8 mo to decide | 6 | Planning Permission Expired | 2015-12-17 |
Derrynaveigh Wind Farm Derrynaveigh Wind Farm Ltd · L/2013/0623/F · 22.1 mo to decide | 5.6 | Application Refused | 2015-09-24 |
Garranbane Wind Farm Garranbane Wind Farm Ltd · L/2013/0622/F · 19.9 mo to decide | 8 | Appeal Withdrawn | 2015-07-20 |
Slieveard Wind Farm Slieveard Wind Farm Ltd · K/2013/0102/F · 27.7 mo to decide | 17.5 | Appeal Withdrawn | 2015-07-16 |
Clunahill Wind Farm ESB (Hibernian Wind) · K/2007/0547/F · 87.9 mo to decide | 21 | Awaiting Construction | 2015-02-20 |
Altamuskin Extension Altamuskin Windfarm (Energia) · K/2011/0239/F · 45.5 mo to decide | 7.1 | Operational | 2015-01-28 |
Teiges Energia · L/2008/0459/F · 80.4 mo to decide | 11 | Operational | 2014-12-12 |
Crocknamona Wind Farm Scottish and Southern Energy (SSE) · K/2010/0758/F · 46.8 mo to decide | 17.5 | Application Refused | 2014-11-13 |
490m north East of no 64 Backglen Road Private Developer · K/2014/0477/F | 2 | Appeal Withdrawn | 2014-10-23 |
Ref 4920 Private Developer · K/2014/0440/F | 2 | Appeal Withdrawn | 2014-09-29 |
Carricknabrattoge Wind Developments · L/2002/1183/F | 12.1 | Application Withdrawn | 2013-10-08 |
Belmore Mountain Airtricity Developments (UK) · L/2005/0377/F | 30 | Application Withdrawn | 2013-10-08 |
Garrane B9 Wind Farm Developments · L/2001/1346/F | 17.5 | Application Withdrawn | 2013-10-08 |
Slieveglass Slieveglass wind farm (Energia) · J/2008/0088 · 64.5 mo to decide | 6.9 | Operational | 2013-06-12 |
Molly Mountain Erne Concrete Pumping · L/2008/1113/F · 53.6 mo to decide | 15 | Operational | 2013-02-01 |
Pigeon Top Energia · K/2011/0592/F · 13.7 mo to decide | 27 | Under Construction | 2012-11-15 |
Thornog Windfarm Extension Energia Renewables · K/2009/0243/F · 41.4 mo to decide | 9.2 | Operational | 2012-09-11 |
Crockbaravally Wind Farm Golden Square Energy · K/2008/1153/F · 38 mo to decide | 7.5 | Operational | 2012-03-05 |
Castlecraig Renewable Energy Systems (RES) · K/2006/1934/F · 53.5 mo to decide | 25 | Operational | 2011-06-01 |
Ora More Natural Power · L/2005/3070/F · 63.4 mo to decide | 15 | Operational | 2011-03-30 |
Tullinoid Fermanagh Wind Energy · L/2004/0472/F | 6 | Application Withdrawn | 2011-01-18 |
Pigeon Top TCI Renewables · K/2009/0081 · 23.1 mo to decide | 20.7 | Revised | 2010-12-13 |
Crockagarron Ext Northern Wind Power� · K/2009/0182/F · 21.2 mo to decide | 2.5 | Operational | 2010-12-08 |
Inishative Gaelectric Developments/ CGN Europe Energy · K/2006/1793/F · 48.1 mo to decide | 13.8 | Operational | 2010-11-12 |
Crockdun ESB (Northern Wind Power) · K/2006/0074/F · 55.7 mo to decide | 12.5 | Operational | 2010-09-13 |
Cregganconroe Gaelectric Developments/ CGN Europe Energy · K/2006/0242/F · 47.3 mo to decide | 13.8 | Operational | 2010-09-08 |
Callagheen Ext Scottish Power Renewables · L/2007/1772/F | 13.8 | Application Withdrawn | 2010-04-01 |
Pollnalaght (Cornavarrow) Energia · K/2006/1368/F · 39.8 mo to decide | 38.4 | Operational | 2009-10-16 |
Gortgall Unknown · L/2006/1197 · 40.7 mo to decide | 18.4 | Application Refused | 2009-07-21 |
Ballyreagh, Tempo TCI Renewables · L/2006/2371/F · 28.8 mo to decide | 2.5 | Abandoned | 2009-05-11 |
Gortfinbar Energia Renewables · K/2006/1089/F · 37.1 mo to decide | 15 | Operational | 2009-05-07 |
Altamuskin Altamuskin Windfarm (Energia) · K/2006/0164/F · 33.9 mo to decide | 7.1 | Operational | 2008-12-02 |
Screggagh Screggagh Windfarm · K/2005/0810/F · 36.8 mo to decide | 19.5 | Operational | 2008-05-13 |
Tappaghan Extension Greencoat UK Wind · L/2006/1553/F · 34.6 mo to decide | 9 | Operational | 2008-05-01 |
Thornog Windfarm Energia Renewables · K/2005/1786/F · 29.7 mo to decide | 9.2 | Operational | 2008-03-01 |
Crockagarran ESB · K/2005/0537/F · 23.6 mo to decide | 15 | Operational | 2007-06-25 |
Slieve Divena Phase 2 Wind Farm Scottish and Southern Energy (SSE) · K/2005/1691/F · 20.7 mo to decide | 18.8 | Operational | 2007-06-06 |
Slieve Divena Phase 1 Wind Farm Greencoat (formerly Infinis/SSE) · K/2005/0597/F · 26.5 mo to decide | 30 | Operational | 2007-05-17 |
Slieve Rushen Extension Unknown · L/2004/2058/F · 22.9 mo to decide | 54 | Operational | 2006-10-01 |
Land approx 75m South of 141 Private Developer · K/2005/0183/F · 2.7 mo to decide | 20 | Operational | 2005-04-26 |
Callagheen B9 / Renewable Energy Systems (RES) · L2001/1514 · 27.4 mo to decide | 22.8 | Operational | 2004-04-08 |
Tappaghan Greencoat UK Wind · L/2002/1042/F · 15.1 mo to decide | 19.5 | Operational | 2003-11-03 |
Slieve Rushen Phase 1 Wind Farm Sean Quinn Group · 5.6 mo to decide | 5 | Operational | 1992-11-02 |
Does Fermanagh and Omagh approve onshore wind schemes?
Yes — of the 66 onshore wind schemes Fermanagh and Omagh has decided, 92% were approved (61 granted, 5 refused). The UK-wide rate for onshore wind is 68%.
How long does a onshore wind scheme application take in Fermanagh and Omagh?
The median time from application to decision is 20.9 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.
How much onshore wind capacity has Fermanagh and Omagh consented?
552 MW has been consented across 61 approved schemes, with 93 MW refused. A further 12 applications awaits a decision.
Other technologies in Fermanagh and Omagh
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.