Renewable sites › Curraghamulkin (Dooish Wind Farm)
Curraghamulkin (Dooish Wind Farm)
Curraghamulkin (Dooish Wind Farm) is operational in Fermanagh and Omagh with a recorded capacity of 30 MW, and has been generating since 2018-07-15.
Planning and build timeline
| Application submitted | 2008-03-12 |
| Permission granted | 2017-11-10 116 months after submission |
| Operational | 2018-07-15 8 months after consent |
Fermanagh and Omagh’s record on onshore wind
Fermanagh and Omagh has decided 66 onshore wind schemes and approved 92%, taking a median of 20.9 months. See every onshore wind scheme decision in Fermanagh and Omagh →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Pigeon Top Wind Onshore · Under Construction | 27 | 4.3 km |
Thornog Windfarm Extension Wind Onshore · Operational | 9.2 | 4.3 km |
Thornog Windfarm Wind Onshore · Operational | 9.2 | 4.3 km |
Pollnalaght (Cornavarrow) Wind Onshore · Operational | 38.4 | 4.8 km |
Slieveglass Wind Onshore · Operational | 6.9 | 7.3 km |
Castlecraig Wind Onshore · Operational | 25 | 7.6 km |
Lough Hill Wind Onshore · Operational | 10.5 | 8.6 km |
Bin Mountain Wind Onshore · Operational | 9 | 9.2 km |
How big is Curraghamulkin (Dooish Wind Farm)?
Curraghamulkin (Dooish Wind Farm) has a recorded installed capacity of 30 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Curraghamulkin (Dooish Wind Farm)?
REPD records the operator as DW Consultancy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Curraghamulkin (Dooish Wind Farm) approved and built?
The application was submitted on 2008-03-12. Permission was granted on 2017-11-10, 116 months later. The site became operational on 2018-07-15, 8 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4151.