Renewable sites › Slieveglass
Slieveglass
Slieveglass is an operational 6.9 MW onshore wind farm in Fermanagh and Omagh, generating since 10 August 2018. Planning permission was granted on 12 June 2013, 64 months after submission. Operator of record: Slieveglass wind farm (Energia).
Planning and build timeline
| Application submitted | 28 January 2008 |
| Permission granted | 12 June 2013 64 months after submission |
| Operational | 10 August 2018 62 months after consent |
Screening a site of your own?
Fermanagh and Omagh approves 92% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Slieveglass’s recorded coordinate — swap in your own postcode or coordinates.
Fermanagh and Omagh’s record on onshore wind
Fermanagh and Omagh has decided 66 onshore wind schemes and approved 92%, taking a median of 20.9 months. See every onshore wind scheme decision in Fermanagh and Omagh →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 25 | 1.3 km |
Wind Onshore · Operational | 10.5 | 2.3 km |
Wind Onshore · Operational | 9 | 2.4 km |
Wind Onshore · Operational | 9.2 | 3.3 km |
Wind Onshore · Operational | 9.2 | 3.3 km |
Wind Onshore · Operational | 30 | 7.3 km |
Wind Onshore · Operational | 34.5 | 7.9 km |
Wind Onshore · Under Construction | 27 | 9.4 km |
How big is Slieveglass?
Slieveglass has a recorded installed capacity of 6.9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Slieveglass?
REPD records the operator as Slieveglass wind farm (Energia). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Slieveglass approved and built?
The application was submitted on 28 January 2008. Permission was granted on 12 June 2013, 64 months later. The site became operational on 10 August 2018, 62 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4065.