Renewable sites › Castlecraig
Castlecraig
Castlecraig is an operational 25 MW onshore wind farm in Fermanagh and Omagh, generating since 15 August 2018. Planning permission was granted on 1 June 2011, 54 months after submission. Operator of record: Renewable Energy Systems (RES).
Planning and build timeline
| Application submitted | 15 December 2006 |
| Permission granted | 1 June 2011 54 months after submission |
| Operational | 15 August 2018 86 months after consent |
Screening a site of your own?
Fermanagh and Omagh approves 92% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Castlecraig’s recorded coordinate — swap in your own postcode or coordinates.
Fermanagh and Omagh’s record on onshore wind
Fermanagh and Omagh has decided 66 onshore wind schemes and approved 92%, taking a median of 20.9 months. See every onshore wind scheme decision in Fermanagh and Omagh →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Onshore · Operational | 10.5 | 1.2 km |
Wind Onshore · Operational | 6.9 | 1.3 km |
Wind Onshore · Operational | 9 | 1.7 km |
Wind Onshore · Operational | 9.2 | 3.3 km |
Wind Onshore · Operational | 9.2 | 3.3 km |
Wind Onshore · Operational | 30 | 7.6 km |
Wind Onshore · Operational | 34.5 | 8.3 km |
Wind Onshore · Operational | 18.4 | 8.5 km |
How big is Castlecraig?
Castlecraig has a recorded installed capacity of 25 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Castlecraig?
REPD records the operator as Renewable Energy Systems (RES). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Castlecraig approved and built?
The application was submitted on 15 December 2006. Permission was granted on 1 June 2011, 54 months later. The site became operational on 15 August 2018, 86 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4112.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode