Renewable sites › Thompson House Equestrian farm
Thompson House Equestrian farm
Thompson House Equestrian farm is an operational 5 MW solar farm in Wigan, generating since 31 March 2016. Planning permission was granted on 6 February 2015, 4 months after submission. Operator of record: Emotion Solar One.
Planning and build timeline
| Application submitted | 13 October 2014 |
| Permission granted | 6 February 2015 4 months after submission |
| Operational | 31 March 2016 14 months after consent |
Screening a site of your own?
Wigan approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Thompson House Equestrian farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Green Belt — Wigan
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Wigan’s record on solar
Wigan has decided 9 solar farms and approved 100%, taking a median of 1.8 months. See every solar farm decision in Wigan →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Battery · Operational | 30 | 1.9 km |
Landfill Gas · Operational | 4.5 | 3.2 km |
Landfill Gas · Operational | 3 | 4.6 km |
Wind Onshore · Operational | 2.3 | 7.5 km |
Landfill Gas · Operational | 2.1 | 8.4 km |
Solar Photovoltaics · Operational | 0.5 | 8.8 km |
Battery · Under Construction | 49.9 | 9 km |
Solar Photovoltaics · Operational | 2.5 | 9.9 km |
How big is Thompson House Equestrian farm?
Thompson House Equestrian farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Thompson House Equestrian farm?
REPD records the operator as Emotion Solar One. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Thompson House Equestrian farm approved and built?
The application was submitted on 13 October 2014. Permission was granted on 6 February 2015, 4 months later. The site became operational on 31 March 2016, 14 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4785.