Novarly ParcelRenewable sites

Renewable sitesThompson House Equestrian farm

Thompson House Equestrian farm

Thompson House Equestrian farm is an operational 5 MW solar farm in Wigan, generating since 31 March 2016. Planning permission was granted on 6 February 2015, 4 months after submission. Operator of record: Emotion Solar One.

5 MW
Capacity
as recorded in REPD
Operational
Status
since 31 March 2016
Solar Photovoltaics
Technology
Emotion Solar One
Wigan
Authority
England

Planning and build timeline

Application submitted13 October 2014
Permission granted6 February 2015
4 months after submission
Operational31 March 2016
14 months after consent

Screening a site of your own?

RedlineUK · £39

Wigan approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Thompson House Equestrian farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Wigan’s record on solar

Wigan has decided 9 solar farms and approved 100%, taking a median of 1.8 months. See every solar farm decision in Wigan

Other built sites within 15 km

SiteMWDistance
Battery · Operational
301.9 km
Landfill Gas · Operational
4.53.2 km
Landfill Gas · Operational
34.6 km
Wind Onshore · Operational
2.37.5 km
Landfill Gas · Operational
2.18.4 km
Solar Photovoltaics · Operational
0.58.8 km
Battery · Under Construction
49.99 km
Solar Photovoltaics · Operational
2.59.9 km

How big is Thompson House Equestrian farm?

Thompson House Equestrian farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Thompson House Equestrian farm?

REPD records the operator as Emotion Solar One. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Thompson House Equestrian farm approved and built?

The application was submitted on 13 October 2014. Permission was granted on 6 February 2015, 4 months later. The site became operational on 31 March 2016, 14 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4785.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode