Novarly ParcelRenewable sites

Renewable sitesSanko Gosei Solar Panels

Sanko Gosei Solar Panels

Sanko Gosei Solar Panels is an operational 0.5 MW solar farm in West Lancashire, generating since 10 October 2021. Planning permission was granted on 4 February 2021, 2 months after submission. Operator of record: Sanko Gosei UK Limited.

0.5 MW
Capacity
as recorded in REPD
Operational
Status
since 10 October 2021
Solar Photovoltaics
Technology
Sanko Gosei UK Limited
West Lancashire
Authority
England

Planning and build timeline

Application submitted16 December 2020
Permission granted4 February 2021
2 months after submission
Operational10 October 2021
8 months after consent

Screening a site of your own?

RedlineUK · £39

West Lancashire approves 77% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Sanko Gosei Solar Panels’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

West Lancashire’s record on solar

West Lancashire has decided 13 solar farms and approved 77%, taking a median of 1.9 months. See every solar farm decision in West Lancashire

Other built sites within 15 km

SiteMWDistance
Battery · Under Construction
49.90.6 km
Solar Photovoltaics · Operational
2.51.9 km
Battery · Operational
21.9 km
Landfill Gas · Operational
2.95.6 km
Landfill Gas · Operational
1.45.6 km
Landfill Gas · Operational
4.55.7 km
Wind Onshore · Operational
16.7 km
Landfill Gas · Operational
18 km

How big is Sanko Gosei Solar Panels?

Sanko Gosei Solar Panels has a recorded installed capacity of 0.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Sanko Gosei Solar Panels?

REPD records the operator as Sanko Gosei UK Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Sanko Gosei Solar Panels approved and built?

The application was submitted on 16 December 2020. Permission was granted on 4 February 2021, 2 months later. The site became operational on 10 October 2021, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8165.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode