Renewable planning SolarWigan

Solar planning in Wigan

Wigan has decided 9 solar farms and approved 100% of them, taking a median of 1.8 months to decide. Consented capacity: 9 MW. 5 applications still awaiting a decision.

100%
Approved
9 granted · 0 refused
1.8 mo
Median decision
UK 2.3 mo
9 MW
Consented
across approved schemes
0
Appeals
no appeals recorded

How Wigan compares

Against the 298 UK authorities with 5+ solar decisions, Wigan sits in the 77th percentile for approval rate (7 points above the England average) and the 74th percentile for speed.

Decisions by year

35Approved — 1 (2015)115Approved — 1 (2019)119Approved — 1 (2021)121Approved — 2 (2022)222Approved — 1 (2023)123Approved — 2 (2024)224Approved — 1 (2025)125
Approved Refused

Solar decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (17)

SchemeMWStatusDecided
WWL Teaching Hospitals NHS Foundation, The Avenue - Solar Panels
Dalkia Energy Services Limited · A/25/100130/14PDJ
0.71Application Submitted2025-12-18
Guide Dogs For The Blind Association - Solar Panels
Guide Dogs For The Blind Association · A/25/098525/14PDJ · 1.5 mo to decide
0.17Awaiting Construction2025-04-04
Bradley Hall Trading Estate, Bradley Lane - Solar Panels
Industrials Propco 1 · A/24/97565/14PDJ · 2.1 mo to decide
0.42Awaiting Construction2024-09-12
Whitehead Landfill Site, Lower Green Lane - Solar Farm
Whitehead Restoration Limited · PA/2024/0759
10Application Submitted2024-09-05
Wigan Youth Zone - Solar Panels
Wigan Youth Zone · A/24/97506/14PDJ
0.19Application Submitted2024-08-13
Westgate House, Green Street - Solar Panels
Aberla Energy · A/24/97282/14PDJ · 1.8 mo to decide
0.15Awaiting Construction2024-07-08
Whitehead Landfill Site, Lower Green Lane - Solar Farm
Whitehead Restoration Limited · A/24/97074/MAJOR
10Revised2024-04-03
The Range, Parsonage Retail Park - Solar Panels
InRange Limited · A/24/97031/14PDJ
0.2Application Submitted2024-03-28
Robin Park Leisure Centre, Loire Drive - Solar Panels
Wigan Metropolitan Borough Council · A/23/96220/14PDJ · 1.8 mo to decide
0.27Awaiting Construction2023-11-29
Poundland Distribution Centre,Three Sisters Road - Solar Panel
Standard Life Assurance Limited · A/22/93868/FULL · 1.8 mo to decide
2.2Awaiting Construction2022-09-26
Systems Glass - Solar Panels
Thermoseal Group Limited · A/22/93397/14PDJ · 1.1 mo to decide
0.47Awaiting Construction2022-04-26
Wigan Investment Centre - Solar panels
Cactus Energy · A/21/91900/14PDJ · 1.7 mo to decide
0.2Awaiting Construction2021-08-12
Tesco Crab Tree Lane
Tesco Stores · A/18/86499/14PDJ · 1.4 mo to decide
0.5Operational2019-02-01
Cleworth Hall Farm
Solstice Renewables · A/15/81522/MAJOR · 3.9 mo to decide
5Abandoned2016-02-09
Lights Oaks Moss
Earthworm/ EW Capital · A/15/81182/MAJOR · 3 mo to decide
5Abandoned2016-01-22
Mill Farm
RALOS New Energy · A/15/81185/MAJOR · 4.8 mo to decide
5Abandoned2015-12-16
Thompson House Equestrian farm
Emotion Solar One · A/14/79904/MAJOR · 3.8 mo to decide
5Operational2015-02-06

Does Wigan approve solar farms?

Yes — of the 9 solar farms Wigan has decided, 100% were approved (9 granted, 0 refused). The UK-wide rate for solar is 93%.

How long does a solar farm application take in Wigan?

The median time from application to decision is 1.8 months, against a UK median of 2.3 months for solar. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much solar capacity has Wigan consented?

9 MW has been consented across 9 approved schemes. A further 5 applications awaits a decision.

Other technologies in Wigan

Battery storage in WiganOnshore wind in Wigan

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com