Novarly ParcelRenewable sites

Renewable sitesMawdesley Moss

Mawdesley Moss

Mawdesley Moss is an operational 2.3 MW onshore wind farm in Chorley, generating since 1 August 2012. Planning permission was granted on 13 September 2007, 4 months after submission. Operator of record: Private Developer.

2.3 MW
Capacity
as recorded in REPD
Operational
Status
since 1 August 2012
Wind Onshore
Technology
Private Developer
Chorley
Authority
England

Planning and build timeline

Application submitted1 May 2007
Permission granted13 September 2007
4 months after submission
Operational1 August 2012
59 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Chorley: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Mawdesley Moss’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 1 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
1.34.9 km
Battery · Operational
306.4 km
Landfill Gas · Operational
4.56.9 km
Solar Photovoltaics · Operational
57.5 km
Solar Photovoltaics · Operational
2.57.8 km
Battery · Operational
27.8 km
Battery · Under Construction
49.98.1 km
Solar Photovoltaics · Operational
2.58.1 km

How big is Mawdesley Moss?

Mawdesley Moss has a recorded installed capacity of 2.3 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Mawdesley Moss?

REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Mawdesley Moss approved and built?

The application was submitted on 1 May 2007. Permission was granted on 13 September 2007, 4 months later. The site became operational on 1 August 2012, 59 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3944.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode