Renewable sites › The Kingswinford School - Solar panels
The Kingswinford School - Solar panels
The Kingswinford School - Solar panels is operational in Dudley, and has been generating since 2021-12-12.
Planning and build timeline
| Application submitted | 2021-02-25 |
| Permission granted | 2021-10-08 7 months after submission |
| Operational | 2021-12-12 2 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Dudley’s record on solar
Dudley has decided 13 solar farms and approved 100%, taking a median of 1.5 months. See every solar farm decision in Dudley →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Himley Wood Landfill Site Landfill Gas · Operational | 4.4 | 2.1 km |
Dudley EfW EfW Incineration · Operational | 7.4 | 5.5 km |
Cradley Heath Advanced Conversion Technologies · Operational | 1.1 | 6.7 km |
Edwin Richards Landfill Scheme Landfill Gas · Operational | 1.8 | 7.3 km |
Anchor Lane Energy Centre Battery · Operational | 4 | 7.8 km |
Oldbury Advanced Conversion Technologies · Operational | 40 | 9.5 km |
Golds Hill - Battery Storage Battery · Operational | 57 | 10.2 km |
DPD Distribution Centre Solar Photovoltaics · Operational | 1 | 10.7 km |
How big is The Kingswinford School - Solar panels?
REPD does not record an installed capacity for The Kingswinford School - Solar panels.
Who operates The Kingswinford School - Solar panels?
REPD records the operator as Windsor Academy Trust. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was The Kingswinford School - Solar panels approved and built?
The application was submitted on 2021-02-25. Permission was granted on 2021-10-08, 7 months later. The site became operational on 2021-12-12, 2 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8852.