Novarly ParcelRenewable sites

Renewable sitesGolds Hill - Battery Storage

Golds Hill - Battery Storage

Golds Hill - Battery Storage is operational in Sandwell with a recorded capacity of 57 MW, and has been generating since 2024-01-01.

57 MW
Capacity
as recorded in REPD
Operational
Status
since 2024-01-01
Battery
Technology
Constantine Energy Storage ltd
Sandwell
Authority
England

Planning and build timeline

Application submitted2021-05-20
Permission granted2021-08-11
3 months after submission
Operational2024-01-01
29 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Sandwell’s record on battery storage

Sandwell has decided 13 battery storage schemes and approved 92%, taking a median of 2.6 months. See every battery storage scheme decision in Sandwell

Other built sites within 15 km

SiteMWDistance
Wednesbury
EfW Incineration · Under Construction
21.2 km
Oldbury
Advanced Conversion Technologies · Operational
402.8 km
Anchor Lane Energy Centre
Battery · Operational
44 km
DPD Distribution Centre
Solar Photovoltaics · Operational
14.2 km
Kelvin Energy Recovery Facility
EfW Incineration · Under Construction
474.6 km
Kelvin Energy Recovery Facility
EfW Incineration · Under Construction
474.6 km
EPSRC Willenhall
Battery · Operational
25.1 km
Bustleholme Substation
Battery · Operational
49.95.3 km

How big is Golds Hill - Battery Storage?

Golds Hill - Battery Storage has a recorded installed capacity of 57 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Golds Hill - Battery Storage?

REPD records the operator as Constantine Energy Storage ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Golds Hill - Battery Storage approved and built?

The application was submitted on 2021-05-20. Permission was granted on 2021-08-11, 3 months later. The site became operational on 2024-01-01, 29 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9183.

Novarly Parcel · official public data, read properly · parcel.novarly.com