Novarly ParcelRenewable sites

Renewable sitesDudley EfW

Dudley EfW

Dudley EfW is operational in Dudley with a recorded capacity of 7.4 MW, and has been generating since 1998-02-01.

7.4 MW
Capacity
as recorded in REPD
Operational
Status
since 1998-02-01
EfW Incineration
Technology
MES Environmental (CNIM Group)
Dudley
Authority
England

Planning and build timeline

Application submitted1994-09-16
Permission granted1996-02-01
17 months after submission
Operational1998-02-01
24 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Edwin Richards Landfill Scheme
Landfill Gas · Operational
1.82 km
Cradley Heath
Advanced Conversion Technologies · Operational
1.13.5 km
Oldbury
Advanced Conversion Technologies · Operational
404.3 km
Himley Wood Landfill Site
Landfill Gas · Operational
4.44.8 km
DPD Distribution Centre
Solar Photovoltaics · Operational
15.2 km
The Kingswinford School - Solar panels
Solar Photovoltaics · Operational
5.5 km
Anchor Lane Energy Centre
Battery · Operational
45.8 km
Golds Hill - Battery Storage
Battery · Operational
575.9 km

How big is Dudley EfW?

Dudley EfW has a recorded installed capacity of 7.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Dudley EfW?

REPD records the operator as MES Environmental (CNIM Group). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Dudley EfW approved and built?

The application was submitted on 1994-09-16. Permission was granted on 1996-02-01, 17 months later. The site became operational on 1998-02-01, 24 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 813.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council