Dudley EfW is an operational 7.4 MW energy-from-waste plant in Dudley, generating since 1 February 1998. Planning permission was granted on 1 February 1996, 17 months after submission. Operator of record: MES Environmental (CNIM Group).
Planning and build timeline
| Application submitted | 16 September 1994 |
| Permission granted | 1 February 1996 17 months after submission |
| Operational | 1 February 1998 24 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Dudley: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Dudley EfW’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Landfill Gas · Operational | 1.8 | 2 km |
Advanced Conversion Technologies · Operational | 1.1 | 3.5 km |
Advanced Conversion Technologies · Operational | 40 | 4.3 km |
Landfill Gas · Operational | 4.4 | 4.8 km |
Solar Photovoltaics · Operational | 1 | 5.2 km |
Solar Photovoltaics · Operational | — | 5.5 km |
Battery · Operational | 4 | 5.8 km |
Battery · Operational | 57 | 5.9 km |
How big is Dudley EfW?
Dudley EfW has a recorded installed capacity of 7.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Dudley EfW?
REPD records the operator as MES Environmental (CNIM Group). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Dudley EfW approved and built?
The application was submitted on 16 September 1994. Permission was granted on 1 February 1996, 17 months later. The site became operational on 1 February 1998, 24 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 813.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode