Renewable sitesHimley Wood Landfill Site

Himley Wood Landfill Site

Himley Wood Landfill Site is operational in South Staffordshire with a recorded capacity of 4.4 MW, and has been generating since 1996-08-01.

4.4 MW
Capacity
as recorded in REPD
Operational
Status
since 1996-08-01
Landfill Gas
Technology
Biogeneration / Biffa
South Staffordshire
Authority
England

Planning and build timeline

Application submitted1992-11-26
Permission granted1995-03-24
28 months after submission
Operational1996-08-01
16 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
The Kingswinford School - Solar panels
Solar Photovoltaics · Operational
2.1 km
Dudley EfW
EfW Incineration · Operational
7.44.8 km
Anchor Lane Energy Centre
Battery · Operational
45.7 km
Edwin Richards Landfill Scheme
Landfill Gas · Operational
1.86.8 km
Cradley Heath
Advanced Conversion Technologies · Operational
1.17 km
Oldbury
Advanced Conversion Technologies · Operational
408.2 km
Golds Hill - Battery Storage
Battery · Operational
578.4 km
Wednesbury
EfW Incineration · Under Construction
29.2 km

How big is Himley Wood Landfill Site?

Himley Wood Landfill Site has a recorded installed capacity of 4.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Himley Wood Landfill Site?

REPD records the operator as Biogeneration / Biffa. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Himley Wood Landfill Site approved and built?

The application was submitted on 1992-11-26. Permission was granted on 1995-03-24, 28 months later. The site became operational on 1996-08-01, 16 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 554.