Novarly ParcelRenewable planning

Renewable planning Onshore windEast Lindsey

Onshore wind planning in East Lindsey

East Lindsey has decided 14 onshore wind schemes and approved 50% of them, taking a median of 15.9 months to decide. Consented capacity: 70 MW. 2 applications still awaiting a decision.

50%
Approved
7 granted · 7 refused
15.9 mo
Median decision
UK 11.5 mo
70 MW
Consented
81 MW refused
8
Appeals
2 allowed on appeal

How East Lindsey compares

Against the 75 UK authorities with 5+ onshore wind decisions, East Lindsey sits in the 20th percentile for approval rate (18 points below the England average) and the 37th percentile for speed.

Decisions by year

35Refused — 1 (2010)110Refused — 2 (2011)211Approved — 1 (2013)Refused — 1 (2013)213Approved — 1 (2015)Refused — 1 (2015)215Refused — 1 (2017)117
Approved Refused

Onshore wind decisions by the year the decision was issued (Renewable Energy Planning Database). Withdrawn and still-undecided applications are excluded, so a short bar can mean a quiet year rather than a strict council.

Every recorded scheme (19)

SchemeMWStatusDecided
Fen Lane wind farm
Energiekontor UK · N/056/01036/14 · 39.9 mo to decide
17.5Appeal Refused2017-10-25
Damwells Farm
Lantanier UK · N/107/00001/14
10Application Withdrawn2015-10-01
Bank House Farm
REG Windpower · S/039/01184/12
12Application Withdrawn2015-08-03
Asserby wind farm
Energiekontor UK · N/016/01046/14 · 11.7 mo to decide
10Application Refused2015-06-18
Bishopthorpe
Greencoat UK (formerly BayWa r.e.) · N/178/01969/12 · 29.5 mo to decide
16.4Operational2015-03-20
Louth Canal Wind Farm
Partnerships for Renewables · N/133/00586/12 · 12.9 mo to decide
10Appeal Refused2013-04-23
Gayton Le Marsh Wind Farm
Energiekontor UK · N/063/01392/11 · 19.7 mo to decide
16.4Operational2013-04-05
Wainfleet Wind Farm
RWE Npower Renewables · S/195/02532/10
12Application Withdrawn2013-01-21
Langham Wind Farm
RWE Generation UK Plc · N/005/02812/06 · 56.8 mo to decide
12Appeal Refused2011-09-29
Orby Windfarm
Mark Caudwell Ltd · N/084/00642/10 · 11.8 mo to decide
11.7Application Refused2011-03-18
Chase Farm
Enertrag UK Limited · S/011/01270/09 · 17 mo to decide
18.4Appeal Refused2010-12-16
Newton Marsh Wind Project
TCI Renewables · N/178/03348/07 · 15.9 mo to decide
4.6Operational2009-05-28
Orby Windfarm
Mark Caudwell Ltd · N/84/2334/05
54Revised2008-06-25
Withern
Lincolnshire Windpower Limited · N/212/02279/05 · 8.7 mo to decide
1.3Application Refused2006-06-12
Bambers II
Ecotricity Limited · N/187/01107/05 · 4.2 mo to decide
4.6Operational2005-09-08
Fen Farm
Ecotricity · N/36/1046/03 · 16.2 mo to decide
16Operational2004-11-29
The Hollies
National Wind Power · S/039/711/02 · 27.9 mo to decide
2.6Operational2004-10-29
Bambers Farm
Ecotricity · N/110/00269/03 · 3.8 mo to decide
9.6Operational2003-06-15
Orby Windfarm
Mark Caudwell Ltd · 134/2016/02 · 5.9 mo to decide
30Revised2003-06-05

Does East Lindsey approve onshore wind schemes?

Yes — of the 14 onshore wind schemes East Lindsey has decided, 50% were approved (7 granted, 7 refused). The UK-wide rate for onshore wind is 68%.

How long does a onshore wind scheme application take in East Lindsey?

The median time from application to decision is 15.9 months, against a UK median of 11.5 months for onshore wind. That is measured between the submission and decision dates recorded in REPD, so it reflects the whole determination period including any extensions.

How much onshore wind capacity has East Lindsey consented?

70 MW has been consented across 7 approved schemes, with 81 MW refused. A further 2 applications awaits a decision.

Other technologies in East Lindsey

Solar in East LindseyBattery storage in East Lindsey

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0 — 2026 Q1 extract. Approval rate is over decided applications only (approved ÷ approved+refused); withdrawn and undecided schemes are excluded. A permission later expired still counts as approved because consent was granted. REPD covers schemes of roughly 150 kW and above, is published quarterly, and does not record refusal reasons — so nothing here explains why a scheme was refused. Screening context for site selection, not planning advice.

Novarly Parcel · official public data, read properly · parcel.novarly.com

Screen a specific site here · All authorities · UK property report