Renewable sites › Inner Dowsing�
Inner Dowsing�
Inner Dowsing� is an operational 97.2 MW offshore wind farm in DECC (S36), generating since 20 April 2008. Planning permission was granted on 23 September 2003, 12 months after submission. Operator of record: XceCo.
Planning and build timeline
| Application submitted | 11 September 2002 |
| Permission granted | 23 September 2003 12 months after submission |
| Operational | 20 April 2008 55 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in DECC (S36): the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Inner Dowsing�’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
- Special Area of Conservation — Inner Dowsing, Race Bank and North Ridge
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Wind Offshore · Operational | 270 | 3.5 km |
Wind Offshore · Operational | 97.2 | 5.8 km |
Solar Photovoltaics · Operational | 4.9 | 10.7 km |
Wind Offshore · Operational | 283.5 | 11.2 km |
Wind Offshore · Operational | 289.8 | 11.2 km |
Wind Offshore · Operational | 210 | 12.7 km |
Wind Offshore · Operational | 402 | 13.6 km |
Wind Onshore · Operational | 2.6 | 14.6 km |
How big is Inner Dowsing�?
Inner Dowsing� has a recorded installed capacity of 97.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Inner Dowsing�?
REPD records the operator as XceCo. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Inner Dowsing� approved and built?
The application was submitted on 11 September 2002. Permission was granted on 23 September 2003, 12 months later. The site became operational on 20 April 2008, 55 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2491.
Novarly Parcel · official public data, read properly · parcel.novarly.com