THE HOLLIES SOLAR PARK - SKEGNESS

THE HOLLIES SOLAR PARK - SKEGNESS is an operational 8.6 MW solar farm in East Lindsey, generating since 7 June 2013. Planning permission was granted on 19 October 2012, 4 months after submission. Operator of record: Private Developer.

8.6 MW
Capacity
as recorded in REPD
Operational
Status
since 7 June 2013
Solar Photovoltaics
Technology
Private Developer
East Lindsey
Authority
England

Planning and build timeline

Application submitted28 June 2012
Permission granted19 October 2012
4 months after submission
Operational7 June 2013
8 months after consent

Screening a site of your own?

RedlineUK · £39

East Lindsey approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with THE HOLLIES SOLAR PARK - SKEGNESS’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 2 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

East Lindsey’s record on solar

East Lindsey has decided 28 solar farms and approved 100%, taking a median of 3 months. See every solar farm decision in East Lindsey

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
2.60.7 km
Solar Photovoltaics · Operational
11.42.3 km
Solar Photovoltaics · Operational
22.62.9 km
Solar Photovoltaics · Operational
4.94.2 km
Solar Photovoltaics · Under Construction
49.96.5 km
Anaerobic Digestion · Operational
1.413.8 km
Wind Offshore · Operational
97.214.6 km
Wind Offshore · Operational
97.214.8 km

How big is THE HOLLIES SOLAR PARK - SKEGNESS?

THE HOLLIES SOLAR PARK - SKEGNESS has a recorded installed capacity of 8.6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates THE HOLLIES SOLAR PARK - SKEGNESS?

REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was THE HOLLIES SOLAR PARK - SKEGNESS approved and built?

The application was submitted on 28 June 2012. Permission was granted on 19 October 2012, 4 months later. The site became operational on 7 June 2013, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1622.