Renewable sites › Gedney Marsh
Gedney Marsh
Gedney Marsh is an operational 12 MW onshore wind farm in South Holland, generating since 15 July 2008. Planning permission was granted on 27 September 2003, 8 months after submission. Operator of record: Wind Prospect.
Planning and build timeline
| Application submitted | 14 January 2003 |
| Permission granted | 27 September 2003 8 months after submission |
| Operational | 15 July 2008 58 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in South Holland: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Gedney Marsh’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 1 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Anaerobic Digestion · Operational | 1.5 | 1.7 km |
Solar Photovoltaics · Operational | 1 | 5.5 km |
Solar Photovoltaics · Operational | 1.7 | 5.5 km |
Wind Onshore · Operational | 14 | 10.3 km |
Solar Photovoltaics · Operational | 49.9 | 10.5 km |
Solar Photovoltaics · Operational | 12.7 | 10.7 km |
Battery · Under Construction | 250 | 12.8 km |
Solar Photovoltaics · Under Construction | 40 | 14.1 km |
How big is Gedney Marsh?
Gedney Marsh has a recorded installed capacity of 12 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Gedney Marsh?
REPD records the operator as Wind Prospect. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Gedney Marsh approved and built?
The application was submitted on 14 January 2003. Permission was granted on 27 September 2003, 8 months later. The site became operational on 15 July 2008, 58 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3133.