Renewable sites › Gedney Marsh
Gedney Marsh
Gedney Marsh is operational in South Holland with a recorded capacity of 12 MW, and has been generating since 2008-07-15.
Planning and build timeline
| Application submitted | 2003-01-14 |
| Permission granted | 2003-09-27 8 months after submission |
| Operational | 2008-07-15 58 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 1 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Manor Farm (Farm AD) Anaerobic Digestion · Operational | 1.5 | 1.7 km |
Long Sutton Butterfly And Wildlife Park (extension) Solar Photovoltaics · Operational | 1 | 5.5 km |
Long Sutton Butterfly And Wildlife Park Solar Photovoltaics · Operational | 1.7 | 5.5 km |
The Grange Wind Farm Wind Onshore · Operational | 14 | 10.3 km |
Sutton Bridge Solar Farm Solar Photovoltaics · Operational | 49.9 | 10.5 km |
Grange Farm (Lincolnshire) Solar Photovoltaics · Operational | 12.7 | 10.7 km |
Lapwing Fen 2 - Battery Storage Plant Battery · Under Construction | 250 | 12.8 km |
Walpole Bank Solar Photovoltaics · Under Construction | 40 | 14.1 km |
How big is Gedney Marsh?
Gedney Marsh has a recorded installed capacity of 12 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Gedney Marsh?
REPD records the operator as Wind Prospect. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Gedney Marsh approved and built?
The application was submitted on 2003-01-14. Permission was granted on 2003-09-27, 8 months later. The site became operational on 2008-07-15, 58 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3133.