Teesside EfW
Teesside EfW is an operational 19.2 MW energy-from-waste plant in Stockton-on-Tees, generating since 1 January 1998. REPD does not record the planning grant date. Operator of record: SITA UK.
Planning and build timeline
| Application submitted | not recorded |
| Permission granted | not recorded |
| Operational | 1 January 1998 |
Screening a site of your own?
Redline runs the record on your own boundary in Stockton-on-Tees: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Teesside EfW’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
- Nutrient-neutrality catchment — Teesmouth and Cleveland Coast SPA/Ramsar
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
EfW Incineration · Operational | 10 | 0 km |
EfW Incineration · Operational | 21 | 0 km |
EfW Incineration · Operational | 20.1 | 0.3 km |
EfW Incineration · Operational | 12 | 1.2 km |
Anaerobic Digestion · Operational | 4.8 | 1.9 km |
Biomass (dedicated) · Under Construction | 40 | 2.1 km |
Solar Photovoltaics · Operational | 0.18 | 3 km |
Solar Photovoltaics · Operational | 5 | 4 km |
How big is Teesside EfW?
Teesside EfW has a recorded installed capacity of 19.2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Teesside EfW?
REPD records the operator as SITA UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Teesside EfW approved and built?
REPD does not record a submission date. REPD does not record a grant date. The site became operational on 1 January 1998.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4925.
Novarly Parcel · official public data, read properly · parcel.novarly.com
All sites · Screen your own site · Planning by council · Coal mining search by postcode