Renewable sites › Summerston Landfill
Summerston Landfill
Summerston Landfill is operational in Glasgow City with a recorded capacity of 2.8 MW, and has been generating since 1999-07-28.
Planning and build timeline
| Application submitted | 1998-03-30 |
| Permission granted | 1998-12-01 8 months after submission |
| Operational | 1999-07-28 8 months after consent |
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Mugdock Water Treatment Works - Solar panels Solar Photovoltaics · Operational | 0.75 | 4.7 km |
Barclays Glasgow Campus, Plot 4 - Energy Sustainability Centre EfW Incineration · Operational | — | 7.1 km |
South Clyde Energy Centre EfW Incineration · Under Construction | 45 | 8.1 km |
Hutchesons Grammar School Solar Photovoltaics · Operational | 0.18 | 9 km |
Scottish Water, Buchanan Gate - Hydro Energy Scheme Large Hydro · Under Construction | — | 9.3 km |
Buchanan Gate, Stepps - Solar Panels Solar Photovoltaics · Under Construction | 0.86 | 9.4 km |
Glasgow Renewable Energy and Recycling Centre (ACT) Advanced Conversion Technologies · Operational | 10 | 9.5 km |
Glasgow Renewable Energy and Recycling Centre (Waste AD) Anaerobic Digestion · Operational | 5 | 9.5 km |
How big is Summerston Landfill?
Summerston Landfill has a recorded installed capacity of 2.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Summerston Landfill?
REPD records the operator as Combined Landfill Projects (CLP). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Summerston Landfill approved and built?
The application was submitted on 1998-03-30. Permission was granted on 1998-12-01, 8 months later. The site became operational on 1999-07-28, 8 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 734.