Summerston Landfill

Summerston Landfill is an operational 2.8 MW landfill gas site in Glasgow City, generating since 28 July 1999. Planning permission was granted on 1 December 1998, 8 months after submission. Operator of record: Combined Landfill Projects (CLP).

2.8 MW
Capacity
as recorded in REPD
Operational
Status
since 28 July 1999
Landfill Gas
Technology
Combined Landfill Projects (CLP)
Glasgow City
Authority
Scotland

Planning and build timeline

Application submitted30 March 1998
Permission granted1 December 1998
8 months after submission
Operational28 July 1999
8 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Glasgow City: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Summerston Landfill’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
0.754.7 km
EfW Incineration · Operational
7.1 km
EfW Incineration · Under Construction
458.1 km
Solar Photovoltaics · Operational
0.189 km
Large Hydro · Under Construction
9.3 km
Solar Photovoltaics · Under Construction
0.869.4 km
Advanced Conversion Technologies · Operational
109.5 km
Anaerobic Digestion · Operational
59.5 km

How big is Summerston Landfill?

Summerston Landfill has a recorded installed capacity of 2.8 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Summerston Landfill?

REPD records the operator as Combined Landfill Projects (CLP). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Summerston Landfill approved and built?

The application was submitted on 30 March 1998. Permission was granted on 1 December 1998, 8 months later. The site became operational on 28 July 1999, 8 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 734.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode