Novarly ParcelRenewable sites

Renewable sitesStranoch 2

Stranoch 2

Stranoch 2 is under construction in Scottish Government (S36) with a recorded capacity of 20 MW.

20 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Battery
Technology
EDF Energy
Scottish Government (S36)
Authority
Scotland

Planning and build timeline

Application submitted2018-10-18
Permission granted2021-11-24
37 months after submission
Operationalnot recorded

Scottish Government (S36)’s record on battery storage

Scottish Government (S36) has decided 108 battery storage schemes and approved 94%, taking a median of 17.3 months. See every battery storage scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Kilgallioch wind farm
Wind Onshore · Operational
2395.5 km
Glen App
Wind Onshore · Operational
226.6 km
Artfield Fell
Wind Onshore · Operational
19.57.8 km
Glenchamber Wind Farm
Wind Onshore · Operational
27.59.3 km
Kilgallioch Windfarm (Extension)
Wind Onshore · Under Construction
50.49.6 km
Arecleoch Wind Farm (extension)
Battery · Under Construction
209.6 km
Arecleoch Wind Farm (extension)
Wind Onshore · Under Construction
72.89.6 km
Arecleoch Windfarm
Wind Onshore · Operational
1209.6 km

How big is Stranoch 2?

Stranoch 2 has a recorded installed capacity of 20 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Stranoch 2?

REPD records the operator as EDF Energy. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Stranoch 2 approved and built?

The application was submitted on 2018-10-18. Permission was granted on 2021-11-24, 37 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7306.

Novarly Parcel · official public data, read properly · parcel.novarly.com