Novarly ParcelRenewable sites

Renewable sitesArecleoch Wind Farm (extension)

Arecleoch Wind Farm (extension)

Arecleoch Wind Farm (extension) is a 20 MW battery storage site under construction in Scotland. Planning permission was granted on 16 November 2021, 29 months after submission. Operator of record: ScottishPower Renewables.

20 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Battery
Technology
ScottishPower Renewables
National
Authority
Scotland

Planning and build timeline

Application submitted12 June 2019
Permission granted16 November 2021
29 months after submission
Operationalnot recorded

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Arecleoch Wind Farm (extension)’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented battery storage scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Scottish Government (S36)’s record on battery storage

Scottish Government (S36) has decided 108 battery storage schemes and approved 94%, taking a median of 17.3 months. See every battery storage scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Under Construction
72.80 km
Wind Onshore · Operational
1200 km
Wind Onshore · Operational
567.4 km
Wind Onshore · Operational
2398.9 km
Wind Onshore · Under Construction
50.49.2 km
Battery · Under Construction
209.6 km
Wind Onshore · Operational
19.511 km
Wind Onshore · Operational
27.512 km

How big is Arecleoch Wind Farm (extension)?

Arecleoch Wind Farm (extension) has a recorded installed capacity of 20 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Arecleoch Wind Farm (extension)?

REPD records the operator as ScottishPower Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Arecleoch Wind Farm (extension) approved and built?

The application was submitted on 12 June 2019. Permission was granted on 16 November 2021, 29 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7882.