Novarly ParcelRenewable sites

Renewable sitesArtfield Fell

Artfield Fell

Artfield Fell is operational in Dumfries and Galloway with a recorded capacity of 19.5 MW, and has been generating since 2005-06-23.

19.5 MW
Capacity
as recorded in REPD
Operational
Status
since 2005-06-23
Wind Onshore
Technology
Scottish and Southern Energy (SSE)
Dumfries and Galloway
Authority
Scotland

Planning and build timeline

Application submitted2003-09-24
Permission granted2004-02-01
4 months after submission
Operational2005-06-23
17 months after consent

Dumfries and Galloway’s record on onshore wind

Dumfries and Galloway has decided 55 onshore wind schemes and approved 67%, taking a median of 18.5 months. See every onshore wind scheme decision in Dumfries and Galloway

Other built sites within 15 km

SiteMWDistance
Glenchamber Wind Farm
Wind Onshore · Operational
27.51.5 km
Kilgallioch wind farm
Wind Onshore · Operational
2392.7 km
Kilgallioch Windfarm (Extension)
Wind Onshore · Under Construction
50.43.5 km
Stranoch 2
Battery · Under Construction
207.8 km
Arecleoch Wind Farm (extension)
Battery · Under Construction
2011 km
Arecleoch Wind Farm (extension)
Wind Onshore · Under Construction
72.811 km
Arecleoch Windfarm
Wind Onshore · Operational
12011 km
Barlockhart Moor
Wind Onshore · Operational
8.111.7 km

How big is Artfield Fell?

Artfield Fell has a recorded installed capacity of 19.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Artfield Fell?

REPD records the operator as Scottish and Southern Energy (SSE). Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Artfield Fell approved and built?

The application was submitted on 2003-09-24. Permission was granted on 2004-02-01, 4 months later. The site became operational on 2005-06-23, 17 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4518.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council