Novarly ParcelRenewable sites

Renewable sitesGlen App

Glen App

Glen App is an operational 22 MW onshore wind farm in Dumfries and Galloway, generating since 15 January 2017. Planning permission was granted on 4 June 2015, 32 months after submission. Operator of record: Scottish Power Renewables.

22 MW
Capacity
as recorded in REPD
Operational
Status
since 15 January 2017
Wind Onshore
Technology
Scottish Power Renewables
Dumfries and Galloway
Authority
Scotland

Planning and build timeline

Application submitted2 October 2012
Permission granted4 June 2015
32 months after submission
Operational15 January 2017
19 months after consent

Screening a site of your own?

RedlineUK · £39

Dumfries and Galloway approves 67% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Glen App’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Dumfries and Galloway’s record on onshore wind

Dumfries and Galloway has decided 55 onshore wind schemes and approved 67%, taking a median of 18.5 months. See every onshore wind scheme decision in Dumfries and Galloway

Other built sites within 15 km

SiteMWDistance
Battery · Under Construction
206.6 km
Wind Onshore · Operational
23912.1 km
Wind Onshore · Operational
19.514.2 km
Wind Onshore · Operational
12014.5 km
Wind Onshore · Under Construction
72.814.5 km
Battery · Under Construction
2014.5 km

How big is Glen App?

Glen App has a recorded installed capacity of 22 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Glen App?

REPD records the operator as Scottish Power Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Glen App approved and built?

The application was submitted on 2 October 2012. Permission was granted on 4 June 2015, 32 months later. The site became operational on 15 January 2017, 19 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4593.