Renewable sites › Kilgallioch Windfarm (Extension)
Kilgallioch Windfarm (Extension)
Kilgallioch Windfarm (Extension) is under construction in Scottish Government (S36) with a recorded capacity of 50.4 MW.
Planning and build timeline
| Application submitted | 2019-12-16 |
| Permission granted | 2021-12-08 24 months after submission |
| Operational | not recorded |
Scottish Government (S36)’s record on onshore wind
Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Artfield Fell Wind Onshore · Operational | 19.5 | 3.5 km |
Glenchamber Wind Farm Wind Onshore · Operational | 27.5 | 3.6 km |
Kilgallioch wind farm Wind Onshore · Operational | 239 | 4.2 km |
Arecleoch Wind Farm (extension) Battery · Under Construction | 20 | 9.2 km |
Arecleoch Wind Farm (extension) Wind Onshore · Under Construction | 72.8 | 9.2 km |
Arecleoch Windfarm Wind Onshore · Operational | 120 | 9.2 km |
Stranoch 2 Battery · Under Construction | 20 | 9.6 km |
Barlockhart Moor Wind Onshore · Operational | 8.1 | 14.6 km |
How big is Kilgallioch Windfarm (Extension)?
Kilgallioch Windfarm (Extension) has a recorded installed capacity of 50.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Kilgallioch Windfarm (Extension)?
REPD records the operator as ScottishPower Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Kilgallioch Windfarm (Extension) approved and built?
The application was submitted on 2019-12-16. Permission was granted on 2021-12-08, 24 months later. The site is recorded as under construction and has no operational date yet.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 7340.
Novarly Parcel · official public data, read properly · parcel.novarly.com