Kilgallioch wind farm is an operational 239 MW onshore wind farm in Scotland, generating since 15 December 2017. Planning permission was granted on 21 February 2013, 36 months after submission. Operator of record: Scottish Power Renewables.

239 MW
Capacity
as recorded in REPD
Operational
Status
since 15 December 2017
Wind Onshore
Technology
Scottish Power Renewables
National
Authority
Scotland

Planning and build timeline

Application submitted5 March 2010
Permission granted21 February 2013
36 months after submission
Operational15 December 2017
58 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the same record on your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Kilgallioch wind farm’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Wind Onshore · Operational
19.52.7 km
Wind Onshore · Operational
27.54.1 km
Wind Onshore · Under Construction
50.44.2 km
Battery · Under Construction
205.5 km
Battery · Under Construction
208.9 km
Wind Onshore · Under Construction
72.88.9 km
Wind Onshore · Operational
1208.9 km
Wind Onshore · Operational
2212.1 km

How big is Kilgallioch wind farm?

Kilgallioch wind farm has a recorded installed capacity of 239 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Kilgallioch wind farm?

REPD records the operator as Scottish Power Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Kilgallioch wind farm approved and built?

The application was submitted on 5 March 2010. Permission was granted on 21 February 2013, 36 months later. The site became operational on 15 December 2017, 58 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4386.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode