Kilgallioch wind farm

Kilgallioch wind farm is operational in Scottish Government (S36) with a recorded capacity of 239 MW, and has been generating since 2017-12-15.

239 MW
Capacity
as recorded in REPD
Operational
Status
since 2017-12-15
Wind Onshore
Technology
Scottish Power Renewables
Scottish Government (S36)
Authority
Scotland

Planning and build timeline

Application submitted2010-03-05
Permission granted2013-02-21
36 months after submission
Operational2017-12-15
58 months after consent

Scottish Government (S36)’s record on onshore wind

Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36)

Other built sites within 15 km

SiteMWDistance
Artfield Fell
Wind Onshore · Operational
19.52.7 km
Glenchamber Wind Farm
Wind Onshore · Operational
27.54.1 km
Kilgallioch Windfarm (Extension)
Wind Onshore · Under Construction
50.44.2 km
Stranoch 2
Battery · Under Construction
205.5 km
Arecleoch Wind Farm (extension)
Battery · Under Construction
208.9 km
Arecleoch Wind Farm (extension)
Wind Onshore · Under Construction
72.88.9 km
Arecleoch Windfarm
Wind Onshore · Operational
1208.9 km
Glen App
Wind Onshore · Operational
2212.1 km

How big is Kilgallioch wind farm?

Kilgallioch wind farm has a recorded installed capacity of 239 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Kilgallioch wind farm?

REPD records the operator as Scottish Power Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Kilgallioch wind farm approved and built?

The application was submitted on 2010-03-05. Permission was granted on 2013-02-21, 36 months later. The site became operational on 2017-12-15, 58 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4386.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council