Renewable sites › Kilgallioch wind farm
Kilgallioch wind farm
Kilgallioch wind farm is operational in Scottish Government (S36) with a recorded capacity of 239 MW, and has been generating since 2017-12-15.
Planning and build timeline
| Application submitted | 2010-03-05 |
| Permission granted | 2013-02-21 36 months after submission |
| Operational | 2017-12-15 58 months after consent |
Scottish Government (S36)’s record on onshore wind
Scottish Government (S36) has decided 173 onshore wind schemes and approved 80%, taking a median of 33.7 months. See every onshore wind scheme decision in Scottish Government (S36) →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Artfield Fell Wind Onshore · Operational | 19.5 | 2.7 km |
Glenchamber Wind Farm Wind Onshore · Operational | 27.5 | 4.1 km |
Kilgallioch Windfarm (Extension) Wind Onshore · Under Construction | 50.4 | 4.2 km |
Stranoch 2 Battery · Under Construction | 20 | 5.5 km |
Arecleoch Wind Farm (extension) Battery · Under Construction | 20 | 8.9 km |
Arecleoch Wind Farm (extension) Wind Onshore · Under Construction | 72.8 | 8.9 km |
Arecleoch Windfarm Wind Onshore · Operational | 120 | 8.9 km |
Glen App Wind Onshore · Operational | 22 | 12.1 km |
How big is Kilgallioch wind farm?
Kilgallioch wind farm has a recorded installed capacity of 239 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Kilgallioch wind farm?
REPD records the operator as Scottish Power Renewables. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Kilgallioch wind farm approved and built?
The application was submitted on 2010-03-05. Permission was granted on 2013-02-21, 36 months later. The site became operational on 2017-12-15, 58 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 4386.
Novarly Parcel · official public data, read properly · parcel.novarly.com