Renewable sites › Stairfoot Battery Storage Facility
Stairfoot Battery Storage Facility
Stairfoot Battery Storage Facility is operational in Barnsley, and has been generating since 2021-07-31.
Planning and build timeline
| Application submitted | 2021-01-04 |
| Permission granted | 2022-11-08 22 months after submission |
| Operational | 2021-07-31 |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Barnsley’s record on battery storage
Barnsley has decided 5 battery storage schemes and approved 100%, taking a median of 6.2 months. See every battery storage scheme decision in Barnsley →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Barnsley Battery Energy Storage Battery · Operational | 40 | 0.2 km |
Tesco Wombwell Lane Solar Photovoltaics · Operational | 0.2 | 1.6 km |
Premier Foods Bakery, Fish Dam Lane - Solar Farm Solar Photovoltaics · Operational | 2 | 3.9 km |
Park Spring Wind Farm Wind Onshore · Operational | 8.6 | 4.1 km |
Barnsley 1.5 Biomass (dedicated) · Operational | 9 | 4.8 km |
Goldthorpe Solar Photovoltaics · Operational | 1.5 | 9.1 km |
South Kirkby Business Park (Waste AD) Anaerobic Digestion · Operational | 6 | 9.2 km |
Bolton Road Waste Treatment and Renewable Energy Facility (Waste AD) Anaerobic Digestion · Operational | 4 | 10 km |
How big is Stairfoot Battery Storage Facility?
REPD does not record an installed capacity for Stairfoot Battery Storage Facility.
Who operates Stairfoot Battery Storage Facility?
REPD records the operator as Noriker Power Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Stairfoot Battery Storage Facility approved and built?
The application was submitted on 2021-01-04. Permission was granted on 2022-11-08, 22 months later. The site became operational on 2021-07-31.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8392.