Novarly ParcelRenewable sites

Renewable sitesBarnsley 1.5

Barnsley 1.5

Barnsley 1.5 is operational in Barnsley with a recorded capacity of 9 MW, and has been generating since 2015-03-06.

9 MW
Capacity
as recorded in REPD
Operational
Status
since 2015-03-06
Biomass (dedicated)
Technology
SPEP
Barnsley
Authority
England

Planning and build timeline

Application submitted2009-12-14
Permission grantednot recorded
Operational2015-03-06

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Stairfoot Battery Storage Facility
Battery · Operational
4.8 km
Barnsley Battery Energy Storage
Battery · Operational
404.9 km
Premier Foods Bakery, Fish Dam Lane - Solar Farm
Solar Photovoltaics · Operational
25.3 km
Tesco Wombwell Lane
Solar Photovoltaics · Operational
0.26.3 km
Park Spring Wind Farm
Wind Onshore · Operational
8.67.5 km
Royd Moor
Wind Onshore · Operational
5.911 km
South Kirkby Business Park (Waste AD)
Anaerobic Digestion · Operational
612.1 km
Spicer Hill Wind Farm
Wind Onshore · Operational
6.912.3 km

How big is Barnsley 1.5?

Barnsley 1.5 has a recorded installed capacity of 9 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Barnsley 1.5?

REPD records the operator as SPEP. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Barnsley 1.5 approved and built?

The application was submitted on 2009-12-14. REPD does not record a grant date. The site became operational on 2015-03-06.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 6164.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council