Premier Foods Bakery, Fish Dam Lane - Solar Farm is operational in Barnsley with a recorded capacity of 2 MW, and has been generating since 2025-12-01.
Planning and build timeline
| Application submitted | 2023-09-11 |
| Permission granted | 2024-04-08 7 months after submission |
| Operational | 2025-12-01 20 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Barnsley’s record on solar
Barnsley has decided 13 solar farms and approved 100%, taking a median of 1.8 months. See every solar farm decision in Barnsley →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Park Spring Wind Farm Wind Onshore · Operational | 8.6 | 2.8 km |
Stairfoot Battery Storage Facility Battery · Operational | — | 3.9 km |
Barnsley Battery Energy Storage Battery · Operational | 40 | 4.1 km |
Tesco Wombwell Lane Solar Photovoltaics · Operational | 0.2 | 5.1 km |
Barnsley 1.5 Biomass (dedicated) · Operational | 9 | 5.3 km |
South Kirkby Business Park (Waste AD) Anaerobic Digestion · Operational | 6 | 6.8 km |
Goldthorpe Solar Photovoltaics · Operational | 1.5 | 10.2 km |
Elmsall Way, South Elmsall - Solar Panels Solar Photovoltaics · Under Construction | 3 | 11 km |
How big is Premier Foods Bakery, Fish Dam Lane - Solar Farm?
Premier Foods Bakery, Fish Dam Lane - Solar Farm has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Premier Foods Bakery, Fish Dam Lane - Solar Farm?
REPD records the operator as Premier Foods Plc. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Premier Foods Bakery, Fish Dam Lane - Solar Farm approved and built?
The application was submitted on 2023-09-11. Permission was granted on 2024-04-08, 7 months later. The site became operational on 2025-12-01, 20 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 16367.