Barnsley Battery Energy Storage

Barnsley Battery Energy Storage is operational in Barnsley with a recorded capacity of 40 MW, and has been generating since 2023-01-01.

40 MW
Capacity
as recorded in REPD
Operational
Status
since 2023-01-01
Battery
Technology
G2 Energy / SMS Energy Services Ltd
Barnsley
Authority
England

Planning and build timeline

Application submitted2017-01-26
Permission granted2017-08-02
6 months after submission
Operational2023-01-01
65 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Barnsley’s record on battery storage

Barnsley has decided 5 battery storage schemes and approved 100%, taking a median of 6.2 months. See every battery storage scheme decision in Barnsley

Other built sites within 15 km

SiteMWDistance
Stairfoot Battery Storage Facility
Battery · Operational
0.2 km
Tesco Wombwell Lane
Solar Photovoltaics · Operational
0.21.4 km
Premier Foods Bakery, Fish Dam Lane - Solar Farm
Solar Photovoltaics · Operational
24.1 km
Park Spring Wind Farm
Wind Onshore · Operational
8.64.2 km
Barnsley 1.5
Biomass (dedicated) · Operational
94.9 km
Goldthorpe
Solar Photovoltaics · Operational
1.59 km
South Kirkby Business Park (Waste AD)
Anaerobic Digestion · Operational
69.3 km
Bolton Road Waste Treatment and Renewable Energy Facility (Waste AD)
Anaerobic Digestion · Operational
49.9 km

How big is Barnsley Battery Energy Storage?

Barnsley Battery Energy Storage has a recorded installed capacity of 40 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Barnsley Battery Energy Storage?

REPD records the operator as G2 Energy / SMS Energy Services Ltd. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Barnsley Battery Energy Storage approved and built?

The application was submitted on 2017-01-26. Permission was granted on 2017-08-02, 6 months later. The site became operational on 2023-01-01, 65 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 20397.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council