Renewable sites › Bolton Road Waste Treatment and Renewable Energy Facility (Waste AD)
Bolton Road Waste Treatment and Renewable Energy Facility (Waste AD)
Bolton Road Waste Treatment and Renewable Energy Facility (Waste AD) is an operational 4 MW anaerobic digestion plant in Rotherham, generating since 13 July 2015. Planning permission was granted on 8 May 2012, 6 months after submission. Operator of record: Shanks Group.
Planning and build timeline
| Application submitted | 25 October 2011 |
| Permission granted | 8 May 2012 6 months after submission |
| Operational | 13 July 2015 38 months after consent |
Screening a site of your own?
Redline runs the record on your own boundary in Rotherham: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Bolton Road Waste Treatment and Renewable Energy Facility (Waste AD)’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Operational | 1.5 | 2.4 km |
Battery · Operational | 0.3 | 5.1 km |
Wind Onshore · Operational | 8 | 5.8 km |
Solar Photovoltaics · Operational | 0.2 | 8.5 km |
Wind Onshore · Operational | 8 | 8.6 km |
Wind Onshore · Operational | 8.6 | 9.3 km |
Battery · Operational | 40 | 9.9 km |
Battery · Operational | — | 10 km |
How big is Bolton Road Waste Treatment and Renewable Energy Facility (Waste AD)?
Bolton Road Waste Treatment and Renewable Energy Facility (Waste AD) has a recorded installed capacity of 4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Bolton Road Waste Treatment and Renewable Energy Facility (Waste AD)?
REPD records the operator as Shanks Group. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Bolton Road Waste Treatment and Renewable Energy Facility (Waste AD) approved and built?
The application was submitted on 25 October 2011. Permission was granted on 8 May 2012, 6 months later. The site became operational on 13 July 2015, 38 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 339.