Renewable sites › St Peters Hall
St Peters Hall
St Peters Hall is operational in Horsham with a recorded capacity of 1.7 MW, and has been generating since 2021-09-01.
Planning and build timeline
| Application submitted | 2021-07-28 |
| Permission granted | 2021-10-20 3 months after submission |
| Operational | 2021-09-01 |
What this site sits on
The recorded coordinate falls on land surveyed as Urban agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Horsham’s record on solar
Horsham has decided 18 solar farms and approved 94%, taking a median of 3.8 months. See every solar farm decision in Horsham →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Land at Christ�s Hospital School Solar Photovoltaics · Operational | 1.1 | 3.1 km |
Broockhurst Wood Landfill Gas · Operational | 2 | 3.4 km |
Brookhurst Wood Gas to Energy Landfill Gas · Operational | 5.1 | 4.9 km |
Brookhurst Wood (Waste AD) Anaerobic Digestion · Operational | 4.5 | 5 km |
Land at Five Oaks Farm Solar Photovoltaics · Operational | 5 | 6.7 km |
Five Oaks Solar Farm Solar Photovoltaics · Operational | 5 | 7.4 km |
Capel Landfill Landfill Gas · Operational | 1 | 8.9 km |
Land off Hooklands Lane Solar Photovoltaics · Operational | 5 | 12.3 km |
How big is St Peters Hall?
St Peters Hall has a recorded installed capacity of 1.7 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates St Peters Hall?
REPD records the operator as Peter Williams Locke King House. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was St Peters Hall approved and built?
The application was submitted on 2021-07-28. Permission was granted on 2021-10-20, 3 months later. The site became operational on 2021-09-01.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 9382.