Novarly ParcelRenewable sites

Renewable sitesBrookhurst Wood Gas to Energy

Brookhurst Wood Gas to Energy

Brookhurst Wood Gas to Energy is an operational 5.1 MW landfill gas site in Horsham, generating since 23 November 2000. Planning permission was granted on 30 July 1999, 3 months after submission. Operator of record: Biffa.

5.1 MW
Capacity
as recorded in REPD
Operational
Status
since 23 November 2000
Landfill Gas
Technology
Biffa
Horsham
Authority
England

Planning and build timeline

Application submitted4 May 1999
Permission granted30 July 1999
3 months after submission
Operational23 November 2000
16 months after consent

Screening a site of your own?

RedlineUK · £39

Redline runs the record on your own boundary in Horsham: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Brookhurst Wood Gas to Energy’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar, battery or onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Anaerobic Digestion · Operational
4.50.1 km
Landfill Gas · Operational
22.3 km
Landfill Gas · Operational
14 km
Solar Photovoltaics · Operational
1.74.9 km
Solar Photovoltaics · Operational
1.17.8 km
Solar Photovoltaics · Operational
59.7 km
Solar Photovoltaics · Operational
59.8 km
Solar Photovoltaics · Operational
0.1911.8 km

How big is Brookhurst Wood Gas to Energy?

Brookhurst Wood Gas to Energy has a recorded installed capacity of 5.1 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Brookhurst Wood Gas to Energy?

REPD records the operator as Biffa. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Brookhurst Wood Gas to Energy approved and built?

The application was submitted on 4 May 1999. Permission was granted on 30 July 1999, 3 months later. The site became operational on 23 November 2000, 16 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 584.