Renewable sites › Brookhurst Wood (Waste AD)
Brookhurst Wood (Waste AD)
Brookhurst Wood (Waste AD) is operational in Horsham with a recorded capacity of 4.5 MW, and has been generating since 2015-07-01.
Planning and build timeline
| Application submitted | 2009-07-31 |
| Permission granted | 2010-10-01 14 months after submission |
| Operational | 2015-07-01 57 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 4 agricultural land.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Brookhurst Wood Gas to Energy Landfill Gas · Operational | 5.1 | 0.1 km |
Broockhurst Wood Landfill Gas · Operational | 2 | 2.4 km |
Capel Landfill Landfill Gas · Operational | 1 | 4 km |
St Peters Hall Solar Photovoltaics · Operational | 1.7 | 5 km |
Land at Christ�s Hospital School Solar Photovoltaics · Operational | 1.1 | 7.9 km |
Five Oaks Solar Farm Solar Photovoltaics · Operational | 5 | 9.7 km |
Land at Five Oaks Farm Solar Photovoltaics · Operational | 5 | 9.8 km |
Oriel High School Solar Photovoltaics · Operational | 0.19 | 11.8 km |
How big is Brookhurst Wood (Waste AD)?
Brookhurst Wood (Waste AD) has a recorded installed capacity of 4.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Brookhurst Wood (Waste AD)?
REPD records the operator as Biffa/West Sussex County Council. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Brookhurst Wood (Waste AD) approved and built?
The application was submitted on 2009-07-31. Permission was granted on 2010-10-01, 14 months later. The site became operational on 2015-07-01, 57 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 312.