Novarly ParcelRenewable sites

Renewable sitesSouthwick Estate

Southwick Estate

Southwick Estate is an operational 48 MW solar farm in Winchester, generating since 10 March 2015. Planning permission was granted on 13 December 2013, 2 months after submission. Operator of record: Bluefield Solar Income Fund.

48 MW
Capacity
as recorded in REPD
Operational
Status
since 10 March 2015
Solar Photovoltaics
Technology
Bluefield Solar Income Fund
Winchester
Authority
England

Planning and build timeline

Application submitted16 October 2013
Permission granted13 December 2013
2 months after submission
Operational10 March 2015
15 months after consent

Screening a site of your own?

RedlineUK · £39

Winchester approves 100% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Southwick Estate’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 4 agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Winchester’s record on solar

Winchester has decided 24 solar farms and approved 100%, taking a median of 2.9 months. See every solar farm decision in Winchester

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
4.54.5 km
Battery · Under Construction
25.1 km
Solar Photovoltaics · Under Construction
4.55.1 km
Landfill Gas · Operational
2.45.4 km
EfW Incineration · Operational
147.2 km
Solar Photovoltaics · Under Construction
1.28.1 km
Solar Photovoltaics · Operational
1.28.3 km
Landfill Gas · Operational
3.59.2 km

How big is Southwick Estate?

Southwick Estate has a recorded installed capacity of 48 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Southwick Estate?

REPD records the operator as Bluefield Solar Income Fund. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Southwick Estate approved and built?

The application was submitted on 16 October 2013. Permission was granted on 13 December 2013, 2 months later. The site became operational on 10 March 2015, 15 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1768.