Paulsgrove Landfill Site
Paulsgrove Landfill Site is operational in Portsmouth with a recorded capacity of 2.4 MW, and has been generating since 1998-02-01.
Planning and build timeline
| Application submitted | 1996-05-03 |
| Permission granted | 1996-07-29 3 months after submission |
| Operational | 1998-02-01 18 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Non Agricultural agricultural land.
- Nutrient-neutrality catchment — Solent: Includes Chichester and Langstone Harbours SPA/Ramsar, Solent and Southampton Water SPA/Ramsar, Solent Maritime SAC, Portsmouth Harbour SPA/Ramsar
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Lakeside Business Park Battery · Under Construction | 2 | 1.3 km |
Lakeside Business Park Solar Photovoltaics · Under Construction | 4.5 | 1.3 km |
Portsmouth International Port - Solar Panels Solar Photovoltaics · Under Construction | 1.2 | 2.7 km |
MMD Shipping Services Solar Photovoltaics · Operational | 1.2 | 2.9 km |
Portsmouth ERF EfW Incineration · Operational | 14 | 3.1 km |
Southwick Estate Solar Photovoltaics · Operational | 48 | 5.4 km |
Newlands Farm Battery Storage Facility Phase 2 Battery · Operational | 40 | 7 km |
Newlands Farm Solar Solar Photovoltaics · Operational | 20.5 | 7.3 km |
How big is Paulsgrove Landfill Site?
Paulsgrove Landfill Site has a recorded installed capacity of 2.4 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Paulsgrove Landfill Site?
REPD records the operator as Associated Energy Projects plc. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Paulsgrove Landfill Site approved and built?
The application was submitted on 1996-05-03. Permission was granted on 1996-07-29, 3 months later. The site became operational on 1998-02-01, 18 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 599.