Portsmouth ERF

Portsmouth ERF is operational in Portsmouth with a recorded capacity of 14 MW, and has been generating since 2005-03-01.

14 MW
Capacity
as recorded in REPD
Operational
Status
since 2005-03-01
EfW Incineration
Technology
Veolia
Portsmouth
Authority
England

Planning and build timeline

Application submitted1998-08-14
Permission granted2001-10-15
38 months after submission
Operational2005-03-01
41 months after consent

What this site sits on

The recorded coordinate falls on land surveyed as Urban agricultural land.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Lakeside Business Park
Battery · Under Construction
22.4 km
Lakeside Business Park
Solar Photovoltaics · Under Construction
4.52.4 km
Portsmouth International Port - Solar Panels
Solar Photovoltaics · Under Construction
1.22.7 km
MMD Shipping Services
Solar Photovoltaics · Operational
1.22.8 km
Paulsgrove Landfill Site
Landfill Gas · Operational
2.43.1 km
Southwick Estate
Solar Photovoltaics · Operational
487.2 km
Southleigh Landfill
Landfill Gas · Operational
3.58.8 km
Newlands Farm Battery Storage Facility Phase 2
Battery · Operational
409.7 km

How big is Portsmouth ERF?

Portsmouth ERF has a recorded installed capacity of 14 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Portsmouth ERF?

REPD records the operator as Veolia. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Portsmouth ERF approved and built?

The application was submitted on 1998-08-14. Permission was granted on 2001-10-15, 38 months later. The site became operational on 2005-03-01, 41 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1017.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council