Renewable sites › Maldon Wycke Solar Farm
Maldon Wycke Solar Farm
Maldon Wycke Solar Farm is an operational 25 MW solar farm in Maldon, generating since 1 October 2024. Planning permission was granted on 8 August 2022, 5 months after submission. Operator of record: Low Carbon UK.
Planning and build timeline
| Application submitted | 23 February 2022 |
| Permission granted | 8 August 2022 5 months after submission |
| Operational | 1 October 2024 26 months after consent |
Screening a site of your own?
Maldon approves 75% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.
Arrives prefilled with Maldon Wycke Solar Farm’s recorded coordinate — swap in your own postcode or coordinates.
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Maldon’s record on solar
Maldon has decided 8 solar farms and approved 75%, taking a median of 4.4 months. See every solar farm decision in Maldon →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Solar Photovoltaics · Under Construction | 49.99 | 8.8 km |
Battery · Under Construction | 20 | 8.8 km |
Solar Photovoltaics · Operational | 5 | 9.7 km |
Wind Onshore · Operational | 20 | 11.1 km |
Solar Photovoltaics · Operational | 0.19 | 11.8 km |
Solar Photovoltaics · Operational | 6.15 | 13.1 km |
Solar Photovoltaics · Operational | 2.8 | 14 km |
Solar Photovoltaics · Operational | 12.2 | 14 km |
How big is Maldon Wycke Solar Farm?
Maldon Wycke Solar Farm has a recorded installed capacity of 25 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Maldon Wycke Solar Farm?
REPD records the operator as Low Carbon UK. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Maldon Wycke Solar Farm approved and built?
The application was submitted on 23 February 2022. Permission was granted on 8 August 2022, 5 months later. The site became operational on 1 October 2024, 26 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8023.