Renewable sitesSOLAR PARK - WHITCHURCH FARM

SOLAR PARK - WHITCHURCH FARM

SOLAR PARK - WHITCHURCH FARM is an operational 6.5 MW solar farm in Somerset, generating since 17 January 2014. Planning permission was granted on 6 November 2012, 7 months after submission. Operator of record: Anesco.

6.5 MW
Capacity
as recorded in REPD
Operational
Status
since 17 January 2014
Solar Photovoltaics
Technology
Anesco
Somerset
Authority
England

Planning and build timeline

Application submitted13 April 2012
Permission granted6 November 2012
7 months after submission
Operational17 January 2014
14 months after consent

Screening a site of your own?

RedlineUK · £39

Somerset approves 86% of solar farms. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with SOLAR PARK - WHITCHURCH FARM’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented solar farm in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Somerset’s record on solar

Somerset has decided 147 solar farms and approved 86%, taking a median of 3 months. See every solar farm decision in Somerset

Other built sites within 15 km

SiteMWDistance
Landfill Gas · Operational
61.6 km
Battery · Under Construction
64.1 km
Solar Photovoltaics · Operational
74.9 km
Wind Onshore · Operational
24.9 km
Solar Photovoltaics · Operational
57.7 km
Biomass (dedicated) · Operational
7.8 km
Solar Photovoltaics · Under Construction
1.787.8 km
Solar Photovoltaics · Operational
2.38.1 km

How big is SOLAR PARK - WHITCHURCH FARM?

SOLAR PARK - WHITCHURCH FARM has a recorded installed capacity of 6.5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates SOLAR PARK - WHITCHURCH FARM?

REPD records the operator as Anesco. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was SOLAR PARK - WHITCHURCH FARM approved and built?

The application was submitted on 13 April 2012. Permission was granted on 6 November 2012, 7 months later. The site became operational on 17 January 2014, 14 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 1620.