Novarly ParcelRenewable sites

Renewable sitesShooters Bottom Wind Park

Shooters Bottom Wind Park

Shooters Bottom Wind Park is an operational 2 MW onshore wind farm in Somerset, generating since 16 June 2008. Planning permission was granted on 18 May 2006, 32 months after submission. Operator of record: Ecotricity.

2 MW
Capacity
as recorded in REPD
Operational
Status
since 16 June 2008
Wind Onshore
Technology
Ecotricity
Somerset
Authority
England

Planning and build timeline

Application submitted15 September 2003
Permission granted18 May 2006
32 months after submission
Operational16 June 2008
25 months after consent

Screening a site of your own?

RedlineUK · £39

Somerset approves 22% of onshore wind schemes. Redline puts that number, and everything else the record holds, against your own boundary: the authority’s actual approval rate and decision times, every designation inside the red line, agricultural grade, 1 m LIDAR earthworks, how contested the grid is, and yield with a P90 — before you spend on a consultant.

Screen a site here£39

Arrives prefilled with Shooters Bottom Wind Park’s recorded coordinate — swap in your own postcode or coordinates.

Consent ClockUK · Free

Granted years ago. Still not built. Every consented onshore wind scheme in the UK, computed against its statutory commencement deadline — which consents are about to lapse, and where.

Open Consent Clock →

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Somerset’s record on onshore wind

Somerset has decided 9 onshore wind schemes and approved 22%, taking a median of 11.7 months. See every onshore wind scheme decision in Somerset

Other built sites within 15 km

SiteMWDistance
Solar Photovoltaics · Operational
70.5 km
Biomass (dedicated) · Operational
2.9 km
Solar Photovoltaics · Operational
2.64.5 km
Solar Photovoltaics · Operational
6.54.9 km
Solar Photovoltaics · Operational
5.45.1 km
Landfill Gas · Operational
66.6 km
Solar Photovoltaics · Operational
3.96.8 km
Solar Photovoltaics · Under Construction
57.7 km

How big is Shooters Bottom Wind Park?

Shooters Bottom Wind Park has a recorded installed capacity of 2 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Shooters Bottom Wind Park?

REPD records the operator as Ecotricity. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Shooters Bottom Wind Park approved and built?

The application was submitted on 15 September 2003. Permission was granted on 18 May 2006, 32 months later. The site became operational on 16 June 2008, 25 months after consent.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 3161.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council · Coal mining search by postcode