Novarly ParcelRenewable sites

Renewable sitesMidsomer Norton - Battery Energy Storage System

Midsomer Norton - Battery Energy Storage System

Midsomer Norton - Battery Energy Storage System is under construction in Bath and North East Somerset with a recorded capacity of 6 MW.

6 MW
Capacity
as recorded in REPD
Under Construction
Status
no operational date
Battery
Technology
Conrad Energy (Developments) II Limited
Bath and North East Somerset
Authority
England

Planning and build timeline

Application submitted2021-07-09
Permission granted2022-12-21
17 months after submission
Operationalnot recorded

What this site sits on

The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.

REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.

Other built sites within 15 km

SiteMWDistance
Langleys Lane - Electricity Generation Plant
Landfill Gas · Operational
62.7 km
SOLAR PARK - WHITCHURCH FARM
Solar Photovoltaics · Operational
6.54.1 km
Chelwood Solar Farm
Solar Photovoltaics · Operational
57.1 km
Hunstrete (Wilmington Farm)
Solar Photovoltaics · Operational
2.37.1 km
Land at Soho Farm
Solar Photovoltaics · Operational
1.57.1 km
Fosseway Environment Park
Anaerobic Digestion · Under Construction
18.2 km
Burges Lane, Stoke St Michael - Solar Array Panels
Solar Photovoltaics · Under Construction
1.788.4 km
Shooters Bottom Solar Park
Solar Photovoltaics · Operational
78.9 km

How big is Midsomer Norton - Battery Energy Storage System?

Midsomer Norton - Battery Energy Storage System has a recorded installed capacity of 6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.

Who operates Midsomer Norton - Battery Energy Storage System?

REPD records the operator as Conrad Energy (Developments) II Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.

When was Midsomer Norton - Battery Energy Storage System approved and built?

The application was submitted on 2021-07-09. Permission was granted on 2022-12-21, 17 months later. The site is recorded as under construction and has no operational date yet.

Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 11866.

Novarly Parcel · official public data, read properly · parcel.novarly.com

All sites · Screen your own site · Planning by council