Langleys Lane - Electricity Generation Plant is operational in Somerset with a recorded capacity of 6 MW, and has been generating since 2021-07-01.
Planning and build timeline
| Application submitted | 2021-03-12 |
| Permission granted | 2021-08-13 5 months after submission |
| Operational | 2021-07-01 |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
SOLAR PARK - WHITCHURCH FARM Solar Photovoltaics · Operational | 6.5 | 1.6 km |
Midsomer Norton - Battery Energy Storage System Battery · Under Construction | 6 | 2.7 km |
Shooters Bottom Solar Park Solar Photovoltaics · Operational | 7 | 6.5 km |
Chelwood Solar Farm Solar Photovoltaics · Operational | 5 | 6.5 km |
Shooters Bottom Wind Park Wind Onshore · Operational | 2 | 6.6 km |
Hunstrete (Wilmington Farm) Solar Photovoltaics · Operational | 2.3 | 6.9 km |
Land at Soho Farm Solar Photovoltaics · Operational | 1.5 | 8.3 km |
Burges Lane, Stoke St Michael - Solar Array Panels Solar Photovoltaics · Under Construction | 1.78 | 8.5 km |
How big is Langleys Lane - Electricity Generation Plant?
Langleys Lane - Electricity Generation Plant has a recorded installed capacity of 6 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Langleys Lane - Electricity Generation Plant?
REPD records the operator as Biogas Technologies Limited. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Langleys Lane - Electricity Generation Plant approved and built?
The application was submitted on 2021-03-12. Permission was granted on 2021-08-13, 5 months later. The site became operational on 2021-07-01.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8840.