Chelwood Solar Farm
Chelwood Solar Farm is operational in Bath and North East Somerset with a recorded capacity of 5 MW, and has been generating since 2015-12-10.
Planning and build timeline
| Application submitted | 2014-05-19 |
| Permission granted | 2014-09-12 4 months after submission |
| Operational | 2015-12-10 15 months after consent |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- Green Belt — Bath and North East Somerset
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Bath and North East Somerset’s record on solar
Bath and North East Somerset has decided 17 solar farms and approved 76%, taking a median of 3.9 months. See every solar farm decision in Bath and North East Somerset →
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Hunstrete (Wilmington Farm) Solar Photovoltaics · Operational | 2.3 | 0.9 km |
Queen Charlton Quarry Renewable Energy Facility - food waste Anaerobic Digestion · Under Construction | 2.2 | 4.8 km |
Langleys Lane - Electricity Generation Plant Landfill Gas · Operational | 6 | 6.5 km |
Midsomer Norton - Battery Energy Storage System Battery · Under Construction | 6 | 7.1 km |
SOLAR PARK - WHITCHURCH FARM Solar Photovoltaics · Operational | 6.5 | 7.7 km |
Fosseway Environment Park Anaerobic Digestion · Under Construction | 1 | 8.2 km |
Shooters Bottom Solar Park Solar Photovoltaics · Operational | 7 | 11.1 km |
Shooters Bottom Wind Park Wind Onshore · Operational | 2 | 11.5 km |
How big is Chelwood Solar Farm?
Chelwood Solar Farm has a recorded installed capacity of 5 MW. That figure is the capacity registered in REPD, which is the scheme as consented — the metered output of a site can differ.
Who operates Chelwood Solar Farm?
REPD records the operator as Mongoose Energy Coop. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Chelwood Solar Farm approved and built?
The application was submitted on 2014-05-19. Permission was granted on 2014-09-12, 4 months later. The site became operational on 2015-12-10, 15 months after consent.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 2298.