Renewable sites › Priddy Road Farm Biomass Boiler (Retrospective)
Priddy Road Farm Biomass Boiler (Retrospective)
Priddy Road Farm Biomass Boiler (Retrospective) is operational in Somerset, and has been generating since 2014-01-29.
Planning and build timeline
| Application submitted | 2020-10-09 |
| Permission granted | 2021-03-08 5 months after submission |
| Operational | 2014-01-29 |
What this site sits on
The recorded coordinate falls on land surveyed as Grade 3 agricultural land. The published survey does not split Grade 3 into 3a and 3b, so this alone does not settle whether the land counts as best and most versatile.
- National Landscape (AONB) — Mendip Hills
REPD gives one representative coordinate per scheme, not the site boundary, so this describes the point on record rather than the whole site — a large site can straddle a designation edge. Boundaries come from planning.data.gov.uk, which publishes for England only.
Other built sites within 15 km
| Site | MW | Distance |
|---|---|---|
Shooters Bottom Wind Park Wind Onshore · Operational | 2 | 2.9 km |
Shooters Bottom Solar Park Solar Photovoltaics · Operational | 7 | 2.9 km |
Pitts Farm Solar Photovoltaics · Operational | 2.6 | 4.3 km |
Crapnell Farm Solar Farm Solar Photovoltaics · Operational | 5.4 | 5 km |
SOLAR PARK - WHITCHURCH FARM Solar Photovoltaics · Operational | 6.5 | 7.8 km |
New Row Farm Solar Photovoltaics · Operational | 3.9 | 8 km |
Framptons Limited Energy Centre Biomass (dedicated) · Under Construction | 3.9 | 8.9 km |
Lodge Farm Solar Farm Solar Photovoltaics · Under Construction | 5 | 9.3 km |
How big is Priddy Road Farm Biomass Boiler (Retrospective)?
REPD does not record an installed capacity for Priddy Road Farm Biomass Boiler (Retrospective).
Who operates Priddy Road Farm Biomass Boiler (Retrospective)?
REPD records the operator as Private Developer. Ownership of built renewable assets changes hands regularly and REPD is published quarterly, so treat this as the operator of record rather than confirmation of who owns it today.
When was Priddy Road Farm Biomass Boiler (Retrospective) approved and built?
The application was submitted on 2020-10-09. Permission was granted on 2021-03-08, 5 months later. The site became operational on 2014-01-29.
Source: Renewable Energy Planning Database (REPD), Department for Energy Security and Net Zero, Open Government Licence v3.0, plus planning designation boundaries from planning.data.gov.uk (England only). REPD is published quarterly and covers schemes of roughly 150 kW and above. Capacity is the installed capacity on record, not metered generation. Operator is the operator of record at the last extract, not confirmation of present ownership. Reference 8241.